Use the fields and options on the Spread Planned Billing dialog box to update the revenue forecast with planned billing from the project plan.
Contents
| Field | Description |
| Selected Range for Spreading
|
Use this option to specify the range for updating the revenue forecast with planned billing values from the plan:
- Spread Planned Billing from Current Period through Plan End Date: Select this option to replace the ETC forecast amounts with published planned billing amounts starting from the first day of the period that contains today through the end of the plan. When you select this option, the planned billing value spreads over the ETC range of the revenue forecast and the
ETC Revenue column on the Revenue Forecast form updates. This is the default setting.
- Spread Planned Billing from Plan Start through Plan End Date: Select this option to replace existing forecast amounts with the published planned billing amounts. The forecast dates are updated to match plan dates. Selecting this option will update the planned revenue in the revenue forecast and spread planned billing from the project plan into the revenue forecast from the plan start through the plan end date.
|
| Planned Amount to Spread
|
This field displays the planned billing amount in the plan's billing currency that will be spread into the revenue forecast. The global revenue forecast settings determine the portion of planned billing that updates the revenue forecast.
|