Contents of the Reschedule Consultant Assignments Dialog Box
Use the Reschedule Consultant Assignments dialog box to change the date ranges of consultant assignments in the plan.
Contents
Field | Description |
---|---|
Consultant Type and Plan Structure Branch | The consultant type and the path through the project work breakdown structure (WBS) to the level of the consultant display in the upper-left corner of the dialog box. |
Shift | Select this option to push the assignment date range forward or backward but keep the same number of working days between the start and end dates.
When you shift date ranges, Vantagepoint keeps the same distribution pattern for planned values. |
Change Duration | Select this option to lengthen or shorten the assignment date range.
When you change the duration of consultant assignment dates, Vantagepoint verifies that the new assignment date range is completely within the applicable plan date range. If the new assignment start and end dates fall outside of the plan dates of the parent row, Vantagepoint prompts you to confirm whether you want to adjust the plan dates to keep the assignment date changes. The following options display when the setting to plan consultants in calendar periods is enabled for the project:
|
From This Assignment Date Range |
These fields display the current assignment start and end dates. If this dialog box displays because you changed a start or end date in the planning grid, or if you selected the
Change Duration option, you cannot change these dates. However, if you clicked
|
To This Assignment Date Range |
Enter the new assignment date range for the row. If you selected the Shift option, you select either a new start or end date, and Vantagepoint determines the other date needed to keep the same number of working days in the range. (If you entered a new start or end date in the planning grid before you displayed this dialog box, that date displays by default, and Vantagepoint calculates the other date. If you did not enter one of the dates in the planning grid before you displayed this dialog box, you enter the new start date, and Vantagepoint calculates the end date.) If you selected the Change Duration option, you select both the start and end dates for the range. |
Buttons
Field | Description |
---|---|
Reschedule | To start the rescheduling process, click
Reschedule.
When you reschedule assignment dates, Vantagepoint does the following:
|
Cancel | To close the dialog box without rescheduling, click this option. |