Contents of the Resource View Form
Use the fields and options on the Resource View form to assign employees and generic resources to projects and enter planned hours for those assignments. You can also use the form to review current and future assignments, view scheduled and utilization percentages, hours, or hours/percentages for your resources, reassign work from one resource to another, or reschedule planned hours.
Videos: See related videos below
The Resource View grid only displays resource assignments for which planned hours exist for dates later than the current job-to-date (JTD) date. The grid only displays planned hours for calendar periods that include the JTD date or that are later than the JTD date.
In addition to assignments that you make using the planning grids, Vantagepoint automatically assigns an employee with no planned hours to a plan work breakdown structure (WBS) element when the employee has JTD hours charged to that WBS element.
Find Resources Pane
Use the Find Resources pane to find and select the resources that you want to assign to projects or for which you want to enter or review planned hours. If the Find Resources pane is not visible to the left of the grid, click in the upper-left corner of the Resource View form to display it.
For descriptions of the fields and options in the pane, see Contents of the Find Resources Pane.
Actions Bar
Click Actions to select one of these options.
Field | Description |
---|---|
Check In Plans |
Select this option to display the Check In Plans dialog box and check in one or more of the plans that are currently checked out. When you select a WBS row in the grid, that project's entire plan is automatically checked out to you. While it is checked out, other users can view it but cannot make changes to it until it is checked back in. Vantagepoint automatically checks in plans when you select a WBS row for a different project, navigate to another part of Vantagepoint, log out of Vantagepoint, navigate to a different URL, use the browser's Refresh option, or close the browser. However, there may be situations in which you must use this option to manually check in plans. |
Select this option to display the Reporting form so you can generate a report. |
Grid Options
Field | Description |
---|---|
Forecast Range |
Click next to this option to display the Change Forecast Range dialog box and define the range of calendar period columns that you want to display in the right grid section. The following settings determine the forecast range:
|
Hide if ETC is Zero | Click
next to this option to display the Hide if ETC is Zero dialog box, where you can filter out projects or resources that have no assigned hours in the selected forecast range.
The dialog box has two options:
The checkboxes in the individual drop-down fields are multi-select. Depending on the options you choose, the toolbar displays Resource, Project, Both, or None. By using this filter, you can simplify the Resource View screen so that it only displays resources and projects with planned hours in the selected forecast range. |
Project Filter |
Click next to this option to display the Filter Project dialog box. The selections that you make on this dialog box determine which projects display in the Resource View grid when you drill down from an employee or generic resource row. The checkboxes in the individual drop-down fields are multi-select (for example, Project Status = Active and/or Inactive and/or Dormant). If you make selections in multiple fields, only projects that satisfy all the selections are displayed in the grid (for example, Project Status = Active or Inactive AND Charge Type = Regular). The employee or resource capacity is not affected by the selected filters. Any rows that would have contributed to the respective employee or generic resource's planned hours display in the Resource View grid as a separate read-only row titled Projects Excluded by Filter. This preserves the total planned hours, with or without filtering projects. If you later add a new assignment that does not meet the project filter criteria, when you click to search again or to reapply the project filter, that newly added project row is not displayed separately and the planned hours are added to the Projects Excluded by Filter row. The following fields are available to filter projects:
|
Show |
Click next to this option to select the type of values that you want to display in the calendar period columns: all planned hours, scheduled hours/percentage, or utilization hours/percentage. When you select scheduled or utilization options, the cell background color indicates the scheduled or utilized status of the resource: gray (proper), blue (under), or red (over). Any calendar cells that are not included in the summary total have the opacity of their font color reduced by 50% to make it clear they are not included in the calculation. Choose from the following options:
For Scheduled Projects: Choose from the following three options for projects where the capacity calculation on the project is set to be included in scheduled. Scheduled hours are planned hours for overhead projects, promotional projects, regular won projects, and any in-pursuit projects that meet the criteria for inclusion in the percentage calculation that are specified on the Plan Settings form (
). The cell background color on the grid indicates the scheduled status: gray (properly scheduled), blue (under-scheduled), or red (over-scheduled).
For Utilization Projects: Choose from the following three options for projects where the capacity calculation on the project is set to included in utilization. These are typically considered billable projects and automatically include all regular won projects and any in-pursuit projects that meet the criteria for inclusion in the percentage calculation that are specified on the Plan Settings form (
). The cell background color on the grid indicates the utilization status: gray (properly utilized), blue (under-utilized), or red (over-utilized).
Generic resources do not have utilization percentages or scheduled percentages, so no values display for those resources if you select Scheduled % or Utilization %. |
<#> Resources Selected |
When you select one or more resources in the grid, the number of selections displays before this field. The count is updated as you select more resources or remove selections. To select all the resource rows in the grid, click the checkbox to the left of this field. You can click this checkbox to clear all selections. If the grid contains more than 50 resources, you cannot use this checkbox. To select resources individually, select the checkbox beside each one in the grid. To clear just your selected resources, click <#> Resources Selected and then click Clear Selections in the info bubble. |
Pin Selected |
To add one or more resources in the grid to your set of pinned resources, select the checkboxes for those resources and click this option. You can then run additional searches and pin other resources that you want to work with. When you finish pinning resources, you can show all the pinned resources in the Resource View grid so that you can make assignments and enter planned hours. |
+ Add Assignments |
To assign work on a project to a group of resources, select the checkboxes for those resources in the Resource View grid and click this option to display the Add Assignments to Selected Resources dialog box. This feature enables you to quickly get a plan started by assigning a group of resources to a project all at once. On the Add Assignments to Selected Resources dialog box, you can select all or some of the resources in the group and then assign those resources to one or more WBS elements. If necessary, you can, without closing the dialog box, select a different set of resources from the group and make different assignments for them. When you have made all assignments for the group of resources and the selected project, you save them all. This option is not available until you select at least one resource. It is also not available if all the resources that you select in the grid are inactive or terminated. You can add assignments only for active resources. |
Save as Search |
To assemble a team of resources that you want to plan for as a group (a project management team, for example) and then save them as a saved search so you can easily display them in the Resource View in the future, select the resources in the Resource View grid and click this option. On the Save Selected dialog box, either specify a name for a new saved search or select an existing saved search to which you want to add the selected resources. |
Pinned |
To display the list of pinned resources on the Pinned dialog box, click this option. On the Pinned dialog box, you can click Show in Grid to display all the pinned resources in the Resource View grid. The number of pinned resources displays next to this toolbar option. |
Click this icon to display the Grid Settings dialog box and do any of the following:
|
Grid Columns: Left Section
This section of the grid displays the resources returned by the search defined in the Find Resources panel and the WBS elements to which each resource was assigned.
To change the width of the left grid section, position your cursor over the dividing line between the left grid section and the middle grid section and then drag the line.
Field | Description |
---|---|
Grouping option |
If you select a grouping option on the Grid Settings dialog box, that option displays as the label of the first column in the upper section of the grid, and the name of each group displays below it in that column. Only groups to which at least one currently selected resource belongs are displayed. Select a group row to display the resources in that group in the lower section of the grid. To change the relative sizes of the upper and lower grid sections, position your cursor over the double line that separates them. When the cursor changes to , click and drag the separator line up or down. |
Resources Selected checkbox |
Use the checkboxes in the first column of the grid to select rows that you want to pin, assign, or save. To select all rows, select the Resources Selected checkbox at the left end of the Resource View toolbar. If more than 50 resources and WBS elements are selected for display in the grid, this checkbox is be disabled. |
Plan availability icons | When you select a WBS row, one of the following icons displays to the left of the top-level WBS element:
Click the icon to display an explanation in an info bubble. If the plan is checked out, the info bubble provides the name and email address of the person who has it checked out. If your security role is an Administrator role, the info bubble also contains a link that you can click to check the plan back in and then check it out to yourself. If the plan has unpublished changes, the info bubble provides the name and email address of the project manager so that you can communicate with them about the plan. |
Resource/Level |
This column displays the resources returned by the search defined in the Find Resources panel and the plan WBS elements (elements from the project WBS and, optionally, labor codes) for which each resource has planned hours. To assign work on a project to a single resource, click the resource row and then click in the Resource/Level field in the row to display the Add Assignments dialog box. If displays in this field where normally does, the resource is inactive or terminated or the WBS element is dormant. The Status column in the middle grid indicates the status for the currently selected WBS row (the project, phase, or task): (Active), (Inactive), (Dormant), or (Terminated). You cannot add new assignments for an inactive or terminated resource or a dormant WBS element (or any elements under it in the WBS), but you can edit, delete, reassign, or reschedule existing assignments. To assign multiple resources to work on the same project, select the checkbox for each of those resources in the Resource View grid and click + Add Assignments on the Resource View toolbar. In addition to resource assignments that you add yourself, the grid may also include assignments for employees with no planned hours but with JTD hours charged to a lowest-level plan element. Vantagepoint creates those assignments automatically. If the relevant branch of the plan WBS either includes the labor code from the time record (exact match or wildcard match), or does not include that labor code but includes other labor codes, that resource assignment is made under the labor code level, based on the time record labor code and the labor code options specified for the plan. If the relevant branch of the plan WBS includes no labor codes, Vantagepoint assumes that you do not want to plan at the labor code level and makes the resource assignment under the lowest-level project WBS element, rather than under a labor code. If the resource is an employee, click the employee name to display information about the employee on the Employee Card dialog box. If the assigned resource is a generic resource, click the resource name to display information about the resource in an info bubble. In WBS rows, click the WBS element to display information about it. You can click the Open in Project View or Open in Projects link in the info bubble to leave Resource View and display the plan for the project in Project View or in the Projects hub. |
Show less and Show more |
Use these links at the top of the Resource/Level column to hide or show the summary columns that you have selected for display in the middle section of the grid. Hiding those columns provides space to display more detail columns. If the summary columns are visible, click Show less to hide them. The link then changes to Show more, which you can click to display the summary columns again. You can pin individual columns if you want them to display even when you click Show less. To do that, click next to the upper-right corner of the grid. On the Grid Settings dialog box, click to the right of those columns to pin them to the grid. |
To assign work on a project to a single resource, do either of the following:
The does not display for a resource row if the resource is inactive or terminated, and it does not display for a WBS row if the WBS element or any element above it in the structure is dormant. You can add assignments only for active resources. You can add assignments for either active or inactive WBS elements. |
Grid Columns: Middle Section
The columns described below are available for display in the middle section of the grid. Click next to the upper-right corner of the grid to select the columns that you want to view.
To change the width of the middle grid section, position your cursor over the dividing line between the middle grid section and the right grid section and then drag the line.
Default Columns:
Field | Description |
---|---|
Status |
This column displays the status of the resource or WBS level: (Active), (Inactive), (Dormant), or (Terminated). |
Has Predecessor | This column displays a checkmark if the WBS level has at least one predecessor. |
Plan Start |
For a WBS row, this column displays the plan start date for the WBS element. If you need to change this date, do that in Project View. |
Plan End |
For a WBS row, this column displays the plan end date for the WBS element. If you need to change this date, do that in Project View. |
Assignment Start |
For a WBS row, this column displays the start date for that resource's assignment to the WBS element. On a row for a lowest-level WBS element, you can enter or select the date. If you change this date and the assignment row has no planned hours, a message displays asking if you want to move the assignment end date as well, to preserve the same number of days between the two dates. If you change this date and the assignment row has planned hours, the Reschedule dialog box displays so you can specify how you want the hours distributed when the assignment is rescheduled. If you change this date in a way that places any part of the assignment date range outside of the plan date range for the row, a message displays asking if you also want to change the plan date range. Click Change Dates to have Vantagepoint adjust the plan dates to include the complete assignment date range. |
Assignment End |
For a WBS row, this column displays the end date for that resource's assignment to the WBS element. On a row for a lowest-level WBS element, you can enter or select the date. If you change this date and the assignment row has planned hours, the Reschedule dialog box displays so you can specify how you want the hours distributed when the assignment is rescheduled. If you change this date in a way that places any part of the assignment date range outside of the plan date range for the row, a message displays asking if you also want to change the plan date range. Click Change Dates to have Vantagepoint adjust the plan dates to include the complete assignment date range. |
Total Planned Hours |
For a WBS row, this column displays the sum of the resource's planned hours for that WBS element for the period from the assignment start date through the assignment end date. For a resource row, this column displays the sum of the resource's planned hours for all WBS elements. |
JTD <date> Hours |
For a WBS row, this column displays the job-to-date (JTD) posted and unposted hours for the employee for that WBS element, through the JTD date. The JTD date displays as part of the column heading. |
Total ETC Hours |
For a WBS row, this column displays the resource's estimate-to-complete (ETC) hours for that WBS element for the period from the assignment start date through the assignment end date. The ETC hours are planned hours for dates in the assignment range beginning the day after the JTD date. For a resource row, this column displays the sum of the resource's ETC hours for all WBS elements. You can enter hours in this field for any WBS element at any level of the plan WBS. When you do, Vantagepoint allocates the hours to calendar periods for that assignment row. If you enter total ETC hours for a parent WBS element and then expand the WBS in the Resource View grid to display assignment rows at lower levels, Vantagepoint further allocates the hours to each calendar period for each lower-level row. Likewise, if you change the scale of the calendar period columns (from Days to Weeks, for example), Vantagepoint reallocates the hours for the new scale. If you enter hours in this field, how the hours are allocated to the calendar period grid columns depends on whether or not ETC hours have already been entered in calendar period columns for the affected assignments:
If the assignment date range includes no more work days that are later than the JTD date, you cannot enter summary hours in this field. |
EAC Hours | This column displays the estimate-at-completion (EAC) hours for the WBS elements and resources: JTD hours + ETC hours. |
Additional Columns:
In addition to the columns displayed by default, you can add the following additional columns from the Grid Settings dialog box:.
Field | Description |
---|---|
Available Scheduled % |
For a resource row, this column displays the available percentage for an employee for the forecast range: 100 - Scheduled % in range. This column is blank for WBS rows. |
Available Utilization % |
For a resource row, this column displays the percentage of available utilization for the forecast range: 100 - Utilization % in range. This column is blank for WBS rows. |
Booking |
This column displays the booking status of each row. If your security role is configured to allow you to hard book assignments, you can select a different booking status for WBS rows. Changing booking status for an assignment does not change any calculated values, nor does it affect your ability to make changes to the assignment dates or hours or to reassign it. What displays in this column, as well as whether or not you can change the booking status, depends on the type of row:
If Vantagepoint is not configured to use soft and hard booking, this column is not available for display. |
Capacity Calculation | This column displays the capacity calculation setting for the individual project. This value is set within the project depending on charge type and stage step, and determines if a project is included or excluded from scheduled and/or utilization calculations. This column is blank at the resource level. |
Charge Type |
This column displays the project charge type: Regular, Promotional, or Overhead. |
Has Successor | This column displays a checkmark if the WBS level has at least one successor. |
Probability |
This column displays the probability percentage of winning the project. |
Project Manager |
This column displays the project manager's name. |
Project Organization Name | If you have implemented organizations in Vantagepoint, this column displays the name of the organization to which the project is assigned. |
Project Status |
This column displays the status of the project: Active, Inactive, or Dormant. |
Range Available Scheduled Hours |
For a resource row. this column displays the available scheduled hours for the forecast range: Working hours in range - Scheduled hours in range. This column is blank for WBS rows. |
Range Available Utilization Hours |
For a resource row, this column displays the available utilization hours for the forecast range: Working hours in range - Utilization hours in range. This column is blank for WBS rows. |
Range ETC Hours |
For a WBS row, this column displays the resource's ETC hours for that assignment for the forecast range. The ETC hours are planned hours for dates in the forecast range beginning the day after the JTD date. For a resource row, this column displays the sum of the resource's ETC hours for all WBS assignments for the forecast range. You can enter hours in this field for any WBS element at any level of the plan WBS. When you do, Vantagepoint allocates the hours to calendar periods for that assignment row that are within the forecast range. If you enter range ETC hours for a parent WBS element and then expand the WBS in the Resource View grid to display rows at lower levels, Vantagepoint further allocates the hours to each calendar period for each lower-level row. Likewise, if you change the scale of the calendar period columns (for example, from Days to Weeks), Vantagepoint reallocates the hours for the new scale. If you enter hours in this field, how the hours are allocated to the calendar period grid columns depends on whether or not ETC hours have already been entered in calendar period columns for the affected assignments:
If the forecast range includes no work days for the assignment that are later than the JTD date, you cannot enter summary hours in this field. |
Range Planned Hours |
For a WBS row, this column displays the sum of the resource's planned hours for that WBS element for the forecast range. For a resource row, this column displays the sum of the resource's planned hours for all WBS elements for the forecast range. |
Range Scheduled Hours |
This column displays the hours planned for the resource in the selected range on projects for which the capacity calculation setting is Include in Scheduled or Include in Scheduled and Utilization. For a WBS row, this column displays the sum of the resource's scheduled hours for that WBS element for the forecast range. For a resource row, this column displays the sum of the resource's scheduled hours for all WBS elements for the forecast range. |
Range Utilization Hours |
For a WBS row, this column displays the sum of the resource's utilization hours for that WBS element for the forecast range. For a resource row, this column displays the sum of the resource's utilization hours for all WBS elements for the forecast range. Utilization hours are planned billable hours: planned hours for won projects and for in pursuit projects that meet the criteria for inclusion in the utilization calculation that are specified on the Plan Settings form ( ). |
Range Working Hours |
This column displays the employee's working hours for the forecast range: Number of working days in the range x employee's hours per day. This column is blank for generic resources and for WBS elements. |
Scheduled % |
This column displays the percent scheduled for an employee: Scheduled hours for the forecast range / Available hours for the forecast range. Scheduled hours are planned hours for overhead projects, promotional projects, regular won projects, and regular in pursuit projects that meet the criteria for inclusion in the percentage calculation that are specified on the Plan Settings form ( ).This column is blank for generic resources and for WBS elements. |
Stage |
This column displays the current stage for the project, such as Awarded, Deferred, Lead, Lost, or Pending. |
Stage Step |
This column displays where the project is in the stage process: Do Not Pursue, In Pursuit, Lost, or Won. |
Utilization % |
This column displays the employee's utilization percentage: Billable planned hours for the forecast range / Available hours for the forecast range. Billable planned hours are planned hours for won projects and for in pursuit projects that meet the criteria for inclusion in the percentage calculation that are specified on the Plan Settings form ( ).This column is blank for generic resources and for WBS elements. |
Utilization Target |
This column displays the employee's target percentage of available hours to be worked on billable projects. This column is blank for generic resources and for WBS elements. |
Grid Columns: Right Section
This grid section displays ETC hours for the forecast range and calendar periods you select.
Field | Description |
---|---|
ETC Before |
For a WBS row, this column displays the sum of the resource's ETC hours for that WBS element for dates after the JTD date and before the start date of the first calendar period column in the forecast range. For a resource row, this column displays the sum of the resource's ETC hours for all WBS elements for dates before the start date of the first calendar period column in the forecast range. You can enter hours in this field for any WBS element at any level of the WBS. If you enter hours for a parent WBS element and then expand the WBS in the Resource View grid to display WBS rows at lower levels,
Vantagepoint further allocates the hours to each lower-level row. How the hours are allocated to lower-level rows depends on whether or not ETC hours have already been entered in calendar period columns for the affected assignments:
If the day following the JTD date falls within the date range for the first calendar period column, no ETC hours exist for dates prior to the forecast range, so this column does not display. |
Calendar period columns |
Use the calendar period columns in the third grid section to view planned hours at the resource level by day, week, or month and to enter or view planned hours for days, weeks, or months on the WBS rows. You can enter hours for any WBS element at any level of the WBS. If you enter hours for a parent WBS element and lower-level WBS elements are displayed, Vantagepoint allocates those hours to the calendar period field for each lower-level WBS row. The forecast range that you specify on the Change Forecast Range dialog box determines the time frame each calendar period column represents. For example, if you set Scale to Weeks, set Duration to 8, and set Start Week to July 1, 2022, the grid displays eight calendar period columns, each column represents a week, and the first calendar period column is for the week that contains July 1, 2022. Using the options in
Show Capacity above the grid, you can also display utilization percentages and scheduled percentages for employees in these columns. (Generic resources do not have utilization percentages or scheduled percentages.) The values in calendar period columns are calculated and displayed as follows, based on your selection in
Show Capacity:
For the WBS level rows, bold values in the calendar columns indicate that the hours for the period are hard booked, and italic values indicate they are either all soft booked or a mix of soft-booked hours and hard-booked hours. You can display columns only for calendar periods that are after the JTD date. However, if a calendar period date range includes at least one day that is later than the JTD date, you can enter planned hours for the resource for that period. To do that, click in that calendar period column to display a drop-down dialog box that shows both the hours for past days in the period and the current ETC hours. You can enter or change the ETC hours. The grid cell then displays the updated sum of the past hours and ETC hours. If you set up multiple companies in Vantagepoint, you can display plans for projects from more than one company in Resource View. Each of those companies could have different starting days for their work weeks. Because of that, Resource View always uses the starting day of the week that is specified for the user's currently active company. |
ETC After |
For a WBS row, this column displays the sum of the resource's ETC hours for that WBS element after the end date of the last calendar period column in the forecast range. For a resource row, this column displays the sum of the resource's ETC hours for dates after the end date of the last calendar period column in the forecast range. You can enter hours in this field for any WBS element at any level of the WBS. If you enter hours for a parent WBS element and then expand the WBS in the Resource View grid to display WBS rows at lower levels,
Vantagepoint further allocates the hours to each lower-level row. How the hours are allocated to lower-level rows depends on whether or not ETC hours have already been entered in calendar period columns for the affected assignments:
|
Row Options
Field | Description |
---|---|
This icon displays at the end of the row when you click or hover over a grid row. Click the icon to select one of these actions for that row:
|
Videos
Title | Description |
---|---|
Learn how to set up the resource planning module, including selecting options for entering and viewing project, opportunity, and resource plans. |
|
Learn how to change the resource assignment dates or duration for an entire plan or for a specific labor assignment. |
|
Learn how to change resource assignments for a project plan. |
|
Learn how to use Project View to review and update resource assignment hours, including estimate-to-complete (ETC) hours, for one or more projects. |
|
Learn how to use Resource View to review and update resource utilization percentages for employees and generic resources assigned to projects. |
|
Learn how to generate reports in Resource Management. You specify which resources are included, the level of the WBS for which you want to see data, and the columns displayed on the report. |
|
Learn how to use the Resource Utilization by Organization report to analyze employee utilization data. |
|
Vantagepoint enables you to set tentatively scheduled labor resource assignments as soft booked and confirmed assignments as hard booked to help manage resource time and workloads. This video demonstrates how to use this feature. |