Display the Redistribute Hours Dialog Box

Display the Redistribute Hours dialog box from the Projects hub.

  1. In the Navigation pane, select Hubs > Projects > Plan.
  2. Select the project for which you want to redistribute hours.
  3. On the Actions bar, click Check Out.
  4. Select the Labor tab.
  5. Expand the plan work breakdown structure (WBS) to display the WBS elements or resource assignments for which you want to redistribute hours.
  6. Hover over the row or click the row, and then click at the end of the row.
  7. Click Redistribute Hours on the menu.