Display the Fill Hours Per Day dialog box from the Projects hub.
-
In the Navigation pane, select
.
-
Select the project and on the Actions bar, click
Check Out.
-
Select the Labor tab.
-
Expand the plan work breakdown structure (WBS) to display the resource assignments for which you want to assign ETC hours.
-
Hover over the row or click the row and then click
at the end of the row.
-
Click
or
Fill Hours Per Day on the menu. (If your user role is not allowed to redistribute hours, the
Distribute Hours option is removed and the
Fill Hours Per Day option moves to the top level of the menu.)
If the plan is checked out but the current ETC date is after the WBS1 plan end date, this option is disabled.