In Resource Planning Settings, use the options on the Plan Settings form to allow expense and consultant planning in calendar periods.
If you set up multiple companies in
Vantagepoint, the decision to enable planning for expenses and consultants in calendar periods is made separately for each company.
To enable the company to plan for expenses and consultants in calendar periods:
-
In the Navigation pane, select
.
-
On the Plan Settings form, set one or both of the following options to
Yes:
Enable Expense Planning and
Enable Consultant Planning.
The
Allow Expense Planning in Calendar Periods and/or
Allow Consultant Planning in Calendar Periods options display.
-
Do either one or both of the following:
- If you enabled expense planning, set the
Allow Expense Planning in Calendar Periods to
Yes.
- If you enabled consultant planning, set the
Allow Consultant Planning in Calendar Periods to
Yes.
-
In the Default Plan Settings When Creating a New Project section of the Plan Settings form:
- Set the
Use Calendar Periods for Expense Planning to
Yes to automatically enable planning expenses in calendar periods for each new project.
- Set the
Use Calendar Periods for Consultant Planning to
Yes to automatically enable planning consultants in calendar periods for each new project.
If your role has access rights to enable or disable planning in calendar periods for individual plans, use the
Plan in Calendar Periods checkbox on the Expenses and/or Consultants tabs of the Plan Settings dialog box in
.
Vantagepoint does not remove any existing plan and baseline data and will restore previously planned values in calendar periods when you re-enable settings.