Display the Reschedule Dialog Box from the Projects Hub

You can display the Reschedule Dialog Box from multiple tabs on the Plan form in the Projects hub.

  1. In the Navigation pane, select Hubs > Projects > Plan.
  2. On the Plan form, select the project for which you want to reschedule plan or assignment dates.
  3. On the Actions bar, click Check Out.
  4. Do one of the following:
    • To reschedule plan dates, go to the Labor, Expenses, Consultants, or Units tab. You can also use the Gantt chart on the Schedule tab to drag the ends of a Gantt bar or drag and move an entire Gantt bar.
    • To reschedule assignments for labor, expenses, consultants, or units, go to the Labor, Expenses, Consultants, or Units tab.
  5. Expand the plan work breakdown structure (WBS) to display the WBS elements, labor, expense, consultant, or unit assignments for which you want to reschedule dates.
  6. Do one of the following:
    • Click at the end of the row for the WBS element or assignment, and then click Reschedule.
    • In the plan or assignment date fields, select a new start or end date.