Revert a Project Plan to the Last Published Version

If you make changes to a project plan and then, before publishing it, you decide you want to discard your changes, you can return the plan to its last published version. As long as you do not publish the plan with your changes, you can revert to the last published version whether or not you have checked in the plan with those changes.

If you have saved a new baseline version of the plan since you last published the plan, the baseline plan also reverts to the last published baseline version.

To revert a project plan to the last published version:
  1. In the Navigation pane, select Hubs > Projects > Plan.
  2. At the top of the Plan form, enter either a complete or partial name or number in the Find project lookup field to find and select the project for which you want to revert the plan.
  3. On the Actions bar, click Check Out.
  4. On the Actions bar, click Other Actions > Revert Plan.
  5. When a confirmation message displays, click Yes to revert to the last published version.