Delete a Resource Assignment in Project View
If you assign a resource to work on a project and later want to remove that assignment, you can do that in the Project View grid.
You can also delete resource assignments in the Resource View grid or on the Labor tab of the Plan form in the Projects hub.
If the assignment has job-to-date (JTD) hours or has been saved as part of the baseline plan, you cannot delete the assignment. In those cases, however, you can still use the procedure below to delete all planned hours for the assignment.
To delete a resource assignment in Project View:
- In the Navigation pane, select .
- At the top of the Project View form, enter either a complete or partial name or number in the Find project lookup field to find and select an existing project for which you want to delete an assignment.
- Expand the plan work breakdown structure until the resource assignment row is visible.
- Hover over that assignment row and click at the end of the row.
- Click Delete.
- When the confirmation message displays, click Delete again.
Parent Topic: How to...