Columns for Labor Plan Summary

You can select the columns to display on your report.

Contents

Field Description
% Complete (JTD/Planned EAC) This column displays the percent complete based on estimate-at-completion hours. Vantagepoint calculates the percent complete as follows: JTD Hours / Planned EAC Hours
% Complete (JTD/Planned) This column displays the percent complete based on total planned hours from the current plan. Vantagepoint calculates the percent complete as follows: JTD Hours / Planned Hour
JTD Hours This column displays the actual job-to-date hours worked.
Planned – Planned EAC This column displays the variance between the total planned hours from the current plan and the estimate-at-completion hours: Planned Hours – Planned EAC Hours
Planned EAC Hours This column displays the estimate-at-completion hours for the WBS component. The estimate-at-completion hours are the estimated total number of labor hours necessary to complete work. Vantagepoint calculates the planned estimate-at-completion hours as follows: JTD Hours + ETC Hours
Planned ETC Hours This column displays the estimate-to-completion hours for the WBS component. The estimate-to-completion hours are the estimated number of planned labor hours necessary to complete the work, starting from the date specified on the Date Basis tab.
Planned Hours This column displays the labor hours specified in the plan.
Row Count This column displays the row number of a line item.
Task This column displays the plan work breakdown structure (WBS) elements for each row of planning data.