Display the Reassign Dialog Box from the Projects Hub

You display the dialog box from the planning grid row for the resource assignment that you want to reassign.

  1. In the Navigation pane, select Hubs > Projects > Plan.
  2. Select the project that contains the resource assignment that you want to reassign.
  3. On the Actions bar, click Check Out.
  4. On the Labor tab, expand the work breakdown structure (WBS) to display the row for the assignment that you want to reassign.
  5. Hover over the row or click the row, and click at the end of the row.
  6. Click Reassign on the menu.