Labor Resource Planned and Actuals Options Tab
Use the Options tab to limit the employees or resource categories included on the report.
Field | Description |
---|---|
Format |
Select the type of data that the report displays for each employee:
Your access to labor cost rates and amounts may be restricted by role security. |
Start Date |
Select the start date for the data on the report:
|
Decimal Setting | Select the number of decimal digits to display for amounts:
|
Scale |
Select one of the following period scales for the hours or amounts on the report:
|
Column Width |
Enter the width for the data columns in inches or millimeters, based on which one you selected in the Unit of Measure field on the Layout tab. Enter inches and millimeters with decimals. For example, enter one and a half inches as 1.5. |
Duration | Select the number of reporting periods to display. The related Scale option determines the type of period. For example, if the scale is monthly and you enter 6 here, the report displays data for six monthly periods. |
Report Details
Field | Description |
---|---|
Employees | Select this option to include employees (named resources). To include only selected employees, use the Employee lookup. |
Select Employees | If you select the Employees check box to include employees on the report and you only want to include selected employees, select them in this field. If you do not select employees, the report includes all employees, unless they are excluded by other report options. |
Generic Resources |
Select this option to include generic resource categories (such as architect or geologist). Generic resources can be based on either labor codes or labor categories. When you select this option, but the Budgeted Employees option is not selected, the Project Planning Performance report groups together generic resources with similar labor categories or labor codes based on the generic method of the plan. The labor category or labor code description displays instead of the generic resource name. If different generic resources exist, an asterisk displays after the labor category or labor code description. |
Select Generic Resources | If you select the Generic Resources check box to include generic resources on the report, and you only want to include selected generic resources, select them in this field. If you do not select generic resources, the report includes all generic resources, unless they are excluded by other report options. |
Tasks with No Resources Assigned | Select this check box to include tasks that have no named resources or generic resource categories assigned. |
For Grouping, Use Organization From | Indicate if you want the report to use the employees' organizations or the projects' organizations. When you group the report by organization or by an organization level, Vantagepoint groups by the employee organizations or project organizations, based on your selection in this field. |
Limit to Resources with this Skill | To restrict the employees included on the report to those with a particular skill, select the skill in this field. The report only displays employees for whom the selected skill is listed on the Experience tab of the Employees hub. |