Project Manager Gantt Chart

The top half of the Resourcing Overview / Resourcing workspace uses the Project Manager Gantt Chart (PG), which displays the full project.

If your project has subprojects, you need to select them individually from the project list to view their details. The bottom half uses the Resources Gantt Chart (RG), which shows the resources assigned to the project and their capacity. You can expand each resource to view their tasks on the project.

Each budget line is represented with a blue Gantt bar. The job itself is represented by a green Gantt bar. The start and end of each Gantt bar correspond to the beginning and end of the task.

The PG can display other types of Gantt bars than these, and not all of them have a counterpart as a budget line in Maconomy. The kind of the task is indicated by the icon in front of its name.

Icon People Planner Maconomy
Project Job
Task Budget line of line type Time
Summary Budget line of type Sum/Text
Absence Does not exist. Instead, absence management is handled through the calendar in Maconomy
Milestone
Amount N/A