After a batch of import progress data is completed, you can manually generate the Import Source report in CSV format, detailing the batch data. The Import Source report includes information such as Project Name, Import Time, whether the entire import passed or failed, and other related details.
Use this group box to filter the data displayed in the Import Source report by specifying a date range or batch ID.
Field and Button |
Description |
Start Date |
Use this field to filter import reports that occur on or after the import's start date, based on the date the import progress is submitted. By default, this field displays the date five days earlier than today's date. |
End Date |
Use this field to filter import reports that occur on or before the import's end date, based on the date the import progress is submitted. By default, this field displays today's date. |
Batch ID |
Use this field to filter the import reports by batch ID or a substring of the batch ID entered. |
Export Data |
Click this button to generate the Import Source report in CSV format, which is saved in the ImportSourceReports subfolder of the Integration Process Logs folder. You can view and edit the log file path on the File Folders tab of the System Settings form.
|
This table lists the columns in the Import Source report.
Column |
Description |
Batch ID |
This column displays the batch ID associated with the import instance. |
Project ID |
This column displays the name of the project used in the import. |
Import Status |
This column displays the status of the import. |
User |
This column displays the first and last names of the user who performed the import. |
Import Time |
This column displays the date and time the import progress is submitted. |
Server Name |
This column displays the PM Compass Process server that processed the imported entry. |
Process Start Time |
This column displays the time the PM Compass Process server started processing the imported entry. |
Process End Time |
This column displays the time the PM Compass Process server completed processing the imported entry. |
Source System ID |
This column displays the source of the API process. |
QBD Number |
This column displays the value associated with an import progress entry. |
CA1 |
This column displays the Control Account Field 1 value. |
CA2 |
This column displays the Control Account Field 2 value. |
CA3 |
This column displays the Control Account Field 3 value. |
WP |
This column displays the Work Package value. |
Schedule Project Name |
This column displays the schedule project. |
Activity ID |
This column displays the ID of the project activity. |
Actual Start Date |
This column displays the Actual Start Date for the activity. |
Actual Finish Date |
This column displays the Actual Finish Date for the activity. |
Forecast Start Date |
This column displays the Forecast Start Date for the work package. |
Forecast Finish Date |
This column displays the Forecast Finish Date for the work package. |
Percent Complete |
This column displays the Percent Complete value for the work package. |
Units Complete |
This column displays the Unit Complete value for the work package. |
Expected Finish Date |
This column displays the Expected Finish Date for the activity. |
Not Earlier Than |
This column displays the Not Earlier Than Date for the activity. |
Progress Type |
This column displays the Progress Type value. |
Progress Value |
This column displays the Progress Value. |
Notes |
This column displays the notes associated with the cost or schedule entry.
|
Milestone/Step Notes
|
This column displays the notes associated with the milestone or step.
|
Processed
|
This column indicates whether an imported entry has completed processing, displaying either Y or N. |
Schedule Resource |
This column displays the Schedule Resource value. |
Estimated Remaining |
This column displays the Schedule Estimated Remaining value. |
Schedule Percent Complete |
This column displays the Schedule Percent Complete value. |
Step ID |
This column displays the Step ID for the activity. |
Step Percent Complete |
This column displays the Step Percent Complete value. |
Step Completed |
This column indicates whether an imported entry has completed the step, displaying either Y or N. |
Cost Resource |
This column displays the Cost Resource value. |
Cost Percent Complete |
This column displays the Cost Percent Complete value. |
Milestone ID |
This column displays the Milestone ID. |
Milestone Actual Finish |
This column displays the Milestone Actual Finish date. |
Milestone Forecast Finish |
This column displays the Milestone Forecast Finish date. |
Milestone Percent Complete |
This column displays the Milestone Percent Complete value. |
Batch Error |
This column displays the failure message encountered by the batch during the import. |