Managing Project Milestones
Milestones are events that are used to track specific phases along a project timeline. For each project, you define the event stages of the project within the Classifications section in the General tab of a project. These event stages determine which milestones are applicable to the project and available within the project's Milestones tab.
For each milestone, you must set the planned completion date. Additionally, you can set the duration in days for each milestone, and the priority. A default set of global recipients is assigned to each milestone, and these people are notified when a milestone is set to complete. You can also add additional roles and contacts if you want to notify additional people when a milestone is completed.
- Related Topics:
- Edit Project Milestones
You edit project milestones to update the statuses, priorities, duration, and planned completion dates. - Add Notes to a Project Milestone
You can add notes to a project milestone to provide supporting information about an event. Any contact with access to a project's milestones can view the notes in the Notes column on the Milestones tab. - Add Recipients to a Project Milestone
In addition to the global default recipients assigned to a project milestone, you can add additional project roles or contacts that you want to notify when a milestone event is set to complete. - Add Another Instance of a Project Milestone
You can add another instance of certain project milestones. This is useful if a milestone occurs multiple times within the lifecycle of a project. - Complete a Project Milestone
When a project milestone event is complete, you must sign it off against the project. Once a milestone event is set to complete, it cannot be edited.