Routings Subtask

Use this subtask to define, view, and maintain process routings for parts.

A given part can have multiple routings, each with a different routing number. Routings are used to generate travelers for manufacturing orders and define capacity planning, shop floor control, lead-time calculation, and standard costing information.

Use this subtask whenever you want to define, view, or maintain process routings for parts.

Routing Header

Field Description
Routing Number

Enter the routing number. If this is the first routing record for this part, 1 displays, and the Primary Routing checkbox is automatically selected, but can be cleared. If you enter additional routing records for the same part, each routing number increments sequentially by one digit. You can select only one routing number as the primary routing for the same part.

Description

Enter the description of the routing being added.

Notes

Enter header notes in this text field.

Released Routing

Select this checkbox to release the routing and make it ready for use. This checkbox is unavailable if you selected the Use Separate Routing Release Function checkbox on the Configure Routing Settings screen, in which case you must use the Release Routings screen to release the routing.

If you selected the Release Routing checkbox on the Configure Engineering Change Notice Settings screen, you can release a routing, if it is assigned to an Engineering Change Notice (ECN) found on the Manage Engineering Change Notices, Approve Engineering Change Notices, and/or Update Approved Engineering Change Notices screens. If you selected the Modify Released Routing checkbox in the ECN Corporate Settings block, you can maintain routings that have already been released only in the Manage Engineering Change Notices, Approve Engineering Change Notices, and/or Update Approved Engineering Change Notices screens.

Primary Routing

Select this checkbox to indicate that this is the primary routing for this part. Primary routings are used as defaults for manufacturing orders and costing and capacity planning.

Company

This field displays the company ID assigned to the routing record. This field is hidden if you selected the Separate Items by Company checkbox on the Configure Product Definition Settings screen.

Release Operations

Click the Release Operations button to release all the unreleased routing operations.

Table Window

Field Description
Operation Sequence

Enter the operation number of the routing step. Each routing line requires an operation. This number must be greater than zero.

Step

Enter the routing step number. This number must be greater than zero.

Step Type

Select Step Type from the drop-down list. The values are:

  • Standard
  • Cost
  • Capacity
Operation

Enter, or click to select, the code of the labor or subcontractor operation being performed on this routing step. You can establish operation information on the Manage Labor Operations or Manage Subcontractor Operations screens in Routings.

Operation Type

This column displays the operation type code associated with the Operation entered. If the Operation field is blank, you can click to select an operation through its type. You can establish Operation Types in the Routing Controls menu in the Routings module.

Alternate Operation

If this routing step is part of an alternate operation, this number must be greater than zero.

Labor/Subcontract

This column displays Labor if the operation was established in the Manage Labor Operations screen, or Subcontract if the operation was established on the Manage Subcontractor Operations screen.

Operation Description

This column displays the name of the operation.

Work Center

This column loads the work center ID entered on the Manage Labor Operations screen. for the operation. This field is populated only for labor operations. Work Centers do not apply to subcontractor operations. You can maintain work center information in the Manage Work Centers screen.

Work Center Name

This column displays the name of the work center.

Process Type

Enter, or click to select, the default process type for the operation. If you add a new line that is a labor operation, and the Routing Primary Default Source is Work Center on the Configure Routings Settings screen, the Process Type code assigned to the work center (on the Manage Work Centers screen) populates this field by default. Otherwise, if you selected the Operation option as the Routing Primary Default Source, the labor operation's Process Type code populates this modifiable field by default from the Manage Labor Operations screen.

QC Step

Select the QC Step checkbox if the operation requires quality control on the Shop Floor Control screens in the Manufacturing Orders menu in Production Control. Clear the QC Step checkbox if you do not want the step to require quality control. Depending on whether this is a labor or subcontractor operation, this field defaults from the QC Operation checkbox on either the Manage Labor Operations or Manage Subcontractor Operations screens and can be modified.

SFC Step

Select the SFC Step checkbox if the operation requires users to record a completion on the Shop Floor Control screens in the Manufacturing Orders menu in Production Control. Clear the SFC Step checkbox if you do not want the step to require Shop Floor Control. Depending on whether this is a labor or subcontractor operation, this field defaults from the SFC Operation checkbox on either the Manage Labor Operations or Manage Subcontractor Operations screens and can be modified.

Effective Starting Date

Enter, or click to select, the date when this routing step becomes effective. The As of Date defaults here for new lines but can be modified.

Effective Ending Date

Enter, or click to select, the date when this routing step is no longer effective.

Run Type

Select the Run Type from the drop-down list. This field displays the default Variable or Fixed that determines how unit run hours or fixed lead time are calculated. You can override the default value by selecting Variable if hours are calculated on a per unit basis, or Fixed if hours are not based on order size.

Unit Run Hours

Enter the number of operation hours it takes to complete one unit in this routing step. If you entered a default for the operation on the Manage Labor Operations screen, that number populates this field by default. You can override this default value with a more accurate number.

Operation Released

This checkbox is selected if this routing step is released and ready for use, and is cleared if it is not.

Change User

This column displays the ID of the last user to modify this routing operation after it was initially entered.

Change Date/Time

This column displays the date and time this routing operation was modified.

Entry User

This column displays the ID of the user who initially entered this routing operation.

Entry Date/Time

This column displays the date and time this routing operation was entered.

Organization

This column displays the Organization ID entered on the Manage Labor Operations screen for this labor operation but can modified. You can enter, or click to select, an organization.

Org Name

This column displays the name associated with the specified Organization ID. If an organization is not specified, you can click to select an organization through its name.

Org Abbreviation

This column displays the abbreviation associated with the specified Organization ID. If an organization is not specified, you can enter, or click to select, the abbreviation of the organization that performs this routing step.

Cumulative Unit Run Hours

This column displays the cumulative unit run hours for this routing line when the Alternate Operation is 0, the Run Type is Variable, and the Step Type is Standard.

Setup Hours

Enter the time in hours required to set up a new manufacturing order at the work center for this routing step. This column may already display the setup hours from the Manage Work Centers screen, but you can override the default with another value.

Cumulative Setup Hours

This column displays the cumulative setup run hours for this routing line when the Alternate Operation is 0 and Step Type is Standard.

Move Hours

Enter the time in hours required to move a manufacturing order to the work center for this routing step. The column may already display the move hours from the Manage Work Centers screen, but you can override the default with another value.

Cumulative Move Hours

This column displays the cumulative move hours for this routing line whose Alternate Operation is 0 and Step Type is Standard.

Queue Hours

Enter the time in hours a manufacturing order must wait at the work center for this routing step. The column may already display the queue hours from the Manage Work Centers screen, but you can override the default with another value.

Cumulative Queue Hours

This column displays the cumulative queue hours for this routing line whose Alternate Operation is 0 and Step Type is Standard.

Fixed Lead Time Hours

This column displays the sum of the Setup Hours, Move Hours, and Queue Hours fields for routing lines with a Variable run type. If the Run Type is Fixed, the Unit Run Hours is added.

Cumulative Fixed Lead Time Hours

This column displays the cumulative fixed lead time hours based on the Run Type whose Alternate Operation is 0 and Step Type is Standard.

Overlap Type

Select the Overlap Type from the drop-down list for starting this operation before the previous operation finishes. The values are:

  • None: This type considers that there can be no overlapping between the previous operation and the new one.
  • Setup: This type considers that the setup/configuration for the next operation can begin while the previous operation is still running.
  • Units: If this type is selected, you must enter the units of overlap in the Overlap Quantity field.
  • Hours: If this type is selected, you must enter the hours of overlap in the Overlap Quantity field.
Overlap Quantity

Enter the amount in hours or units by which the start of this operation can overlap the previous one. If you selected None or Setup in the Overlap Type field, this field is disabled and set to zero.

Key Resource

Enter, or click to select, the ID of the key resource consumed by this routing step. You can establish key resources on the Manage Key Resources screen.

Key Resource Description

This column displays the associated description for the selected ID on the Key Resource field. If the Key Resource field is blank, you can click to select a key resource through its description.

U/M

This column displays the unit of measure set up for the key resource.

Key Resource Unit Usage Qty

Enter the number of key resource units consumed by each unit processed in this routing step.

Key Resource Fixed Usage Qty

Enter the number of key resource units consumed by the setup of this routing step.

Currency

This column displays the functional currency of the company ID that is associated with the routing (from the Configure General Ledger Settings screen in General Ledger). You can also establish default currency settings on the Configure Multicurrency Settings screen in Costpoint Multicurrency. This field is hidden if you selected the Separate Items by Company checkbox on the Configure Product Definition Settings screen.

Rate Source

Select the rate source from the drop-down list. This indicates where cost information is taken from when costing the routing step. There are three options, depending on whether the routing line contains a labor or a subcontractor operation:

  • Work Center: Cost information is used only for labor operations, and can be maintained on the Manage Work Centers screen.
  • Operation: Run rate and setup rate cost information is used only for labor operations; standard unit and fixed costs are used only for subcontractor operations. Burden rates can be used for both labor and subcontractor operations.
  • Override: You can enter run rate, setup rate, and burden rate information to override current work center and current operation cost information (labor operations only). You can enter standard unit cost, fixed cost, and burden rate information to override current operation cost information (subcontractor operations only). Overriding cost information is specific to a part/routing.
Current Work Center Run Rate

This column displays the hourly labor rate for manufacturing in this work center. You can modify the run rate in the Run Labor Hourly Rate field on the Manage Work Centers screen. This field is hidden if the routing line contains a subcontractor operation.

Current Work Center Setup Rate

This column displays the hourly labor rate for doing setups in this work center. You can modify the setup rate in the Setup Labor Hourly Rate field on the Manage Work Centers screen. This field will be hidden if the routing line contains a subcontractor operation.

Current Work Center Burden Rate

This column displays the target burden rate to be applied to labor dollars in this work center. You can modify the burden rate in the Labor Burden Rate field on the Manage Work Centers screen. This field is hidden if the routing line contains a subcontractor operation.

Current Operation Run Rate

This column displays the hourly labor rate for this labor operation. You can modify the run rate in the Run Labor Hourly Rate field on the Manage Labor Operations screen. This field is hidden if the routing line contains a subcontractor operation.

Current Operation Setup Rate

This column displays the hourly labor rate for doing setups for this labor operation. You can modify the setup rate in the Setup Labor Hourly Rate field on the Manage Labor Operations screen. This field is hidden if the routing line contains a subcontractor operation.

Current Operation Std Unit Cost

This column displays the standard unit cost of this operation for every item processed. You can modify the standard unit cost in the Standard Order Unit Cost field on the Cost subtask of the Manage Subcontractor Operations screen. This field is hidden if the routing line contains a labor operation.

Current Operation Std Fixed Cost

This column displays the standard fixed cost of this operation for each new purchase order. You can modify the standard unit cost in the Standard Order Fixed Cost field on the Cost subtask of the Manage Subcontractor Operations screen. This field is hidden if the routing line contains a labor operation.

Current Operation Burden Rate

This column displays the target burden rate to be applied to the amount expended by this operation. For labor operations, you can modify this field in the Labor Burden Rate field on the Manage Labor Operations screen. For subcontractor operations, you can modify this field in the Burden Rate field in the Cost subtask on the Manage Subcontractor Operations screen.

Std Hours Run Rate

This column displays the unit run hours from the routing line in the main screen. This field is hidden if the routing line contains a subcontractor operation.

Std Hours Setup Rate

This column displays the setup time in hours for this routing step that was entered in the Unit Run Hours column. This field is hidden if the routing line contains a subcontractor operation.

Override Run Rate

Enter the override hourly labor rate for this routing step. This field is enabled only if you selected Override in the Rate Source field. This field is hidden if the routing line contains a subcontractor operation.

Override Setup Rate

Enter the override hourly labor rate for doing setups for this routing step. This field is enabled only if you selected Override in the Rate Source field. This field is hidden if the routing line contains a subcontractor operation.

Override Std Unit Cost

Enter the override standard unit cost for the outside operation routing step. This field is enabled only if you selected Override in the Rate Source field. This field is hidden if the routing line contains a labor operation.

Override Std Fixed Cost

Enter the override standard fixed cost per order for the outside operation routing step. This field is enabled only if you selected Override in the Rate Source field. This field is hidden if the routing line contains a labor operation.

Override Burden Rate

Enter the target burden rate to be applied to direct dollars expended in this routing step. This field is enabled only if you selected Override in the Rate Source field. This field is hidden if the routing line contains a labor operation.

Notes

Enter notes related to the routing line.

Calculate Totals

Click the Calculate Totals button to recalculate the cumulative lead time hours for the routings lines.

Subtasks

Subtask Description
Routing Line Filter Click this link to open the Routing Line Filter subtask, where you can retrieve routing lines for existing routings on or before a certain date.
Link Configurations Click this link to open the Link Configurations subtask, where you can link a configuration to a part/routing number.
Standard Text Click this link to open the Standard Text subtask, where you can attach a standard text to the routing step.
Documents Click this link to open the Documents subtask, where you can enter or view documents linked to a specific routing line number.
Equipment Click this link to open the Equipment subtask, where you can select the equipment used by this routing step. You cannot specify an equipment if the selected line is a subcontract operation, that is, if the Labor/Subcontract field value is Subcontract.
Labor Classifications Click this link to open the Labor Classifications subtask, where you can select the labor classifications used in the routing step. You can also click the Autoload button in this subtask to load the labor classification from the operation or work center, if the information has been set up on the Manage Work Centers screen and the Manage Labor Operations screen, respectively. You cannot add labor classifications when the selected line is a subcontract operation, that is, if the Labor/Subcontract field value is Subcontract.
Alternate Work Center Click this link to open the Alternate Work Center subtask, where you can view and select an alternate work center for the operation.