Contents of the Configure Manufacturing Order Costing Options Screen

Use the fields and options to configure the Configure Manufacturing Order Costing Options screen.

Default Partial Relief Costing Option

Field Description
Manually Cost

Select this option to set the partial relief default to manually cost the partial relief quantities.

Use Item Standard Cost

Select this option to set the partial relief default to use the item standard cost as the unit cost for partial reliefs.

Use Item Last Cost

Select this option to set the partial relief default to use the item last cost as the unit cost for partial reliefs.

Use Item Project Standard Cost

Select this option to set the partial relief default to use the item/project standard cost as the unit cost for partial reliefs.

Use Item Project Last Cost

Select this option to set the partial relief default to use the item/project last cost as the unit cost for partial reliefs.

Use Inventory Abbreviation's Average Actual Cost

Select this option to set the partial relief default to use the default build-to inventory abbreviation's average actual cost as the unit cost for partial reliefs.

Use Estimate to Complete  % for Remaining Quantities

Select this option to set the partial relief default to load an estimate to complete percentage for any unrelieved quantities.

Default ETC % Enter the default estimate to complete percentage (0-100) for unrelieved parts of a manufacturing order (MO). This field is enabled when you select Use Estimate to Complete % for Remaining Quantities.

MO Allocations

Default Project Options

Field Description
Not Allowed With Other Projects

Select this option to set the project default to not allow multiple project MOs.

Allowed Within Same Top-Level Project

Select this option to set the project default to allow multiple project MOs only when the projects share the same top-level project.

Allowed Within Same Netting Group

Select this option to set the project default to allow multiple project MOs only when the projects share the same netting group.

Allowed with Other Projects

Select this option to set the project default to allow multiple project MOs.

Allow Allocation Changes in PC Expediting Screen

Select this check box to allow users to modify MO allocation inventory abbreviations on the Expedite Manufacturing Orders screen.

Use Standard Costs for Reliefs of Labor, Misc 1 and Misc 2 Elements (Default)

Select this check box to use standard costs from Project Item Cost (if available) or from Item Cost, instead of actual costs for MO reliefs when calculating the inventory value of labor, Misc 1 and Misc 2 cost elements. This setting displays as the default on the Manage Inventory Projects screen, and can be modified there to override this setting. When this check box is selected for a particular project, all MO's relieved to this project use standard rates (from project item cost or item cost) for labor, Misc 1 and Misc 2 cost elements. This also applies to partial reliefs, regardless of what costing option is selected.