Field Descriptions

 

 

Project Status

What can I do in this subtask?

Use this subtask to view the same information that is printed on the project status report. Use the Update Project Status Report Table screen if no information is displayed in this subtask for the period selected. If you run the process and still do not see data in this subtask, no charges exist for that period.

This subtask consists of one block, the Project Status Child table, and four subtasks.  They can be used, as follows:

When should I use this subtask?

Use this subtask after you have run the Update Project Status Report Table screen.

Field Descriptions

Project Status

Use the fields in this block to review the rate type, project, organization, period information, customer name, contract value, period of performance, total units, and total hours for the row selected in the main screen.

Rate Type

This non-editable field displays the rate type that you selected on the main screen.

Fiscal Year

This non-editable field displays the fiscal year that you entered when you created the project report table.

Period

This non-editable field displays the period that you entered when you created the project report table.

Subperiod

This non-editable field displays the subperiod that you entered when you created the project report table.

Project

This non-editable field displays a project number for the project you want to review.

Organization

This non-editable field displays the owning organization for the project on the main screen.

Period of Performance

This non-editable field displays the start date of the period of performance for the project selected on the main screen.

To

This non-editable field displays the ending date of the period of performance of the project selected in the main screen.

Customer Name

This non-editable field displays the customer name of the project selected on the main screen.

Total Units

This non-editable field displays the total units incurred for the project selected on the main screen.

Total Hours

This non-editable field displays the total hours for the project selected on the main screen.

Contract Value

Use the fields in this group box to review the contract total cost, total fee, total value, and award fee for the project selected on the main screen.

Cost

This non-editable field displays the cost portion of the contract value for the project selected on the main screen.

The contract cost, fee, and total value are entered in the Enter Project Modifications screen (Projects\Transactions\Project).

Fee

This non-editable field displays the fee portion of the contract value for the project selected on the main screen.

The contract cost, fee, and total value are entered in the Enter Project Modifications screen (Projects\Transactions\Project).

Total

This non-editable field displays the total contract value for the project selected on the main screen.

The contract cost, fee, and total value are entered in the Enter Project Modifications screen (Projects\Transactions\Project).

Award Fee

This non-editable field displays the total contact value award fee for the project selected on the main screen. This value is the sum of the Contract Award Fee column from the Award Fee subtask of the Enter Project Modifications screen (Projects\Transactions\Project).

Project Status Child

Use the fields in this table window to review the information that is printed on a project status report.

The information in the table window is broken down into several types of rows:

Different columns in the table display actual or target costs (depending on the rate type selected on the main screen), budget information, and variances for the subperiod, period, YTD, and ITD. The subperiod, period, and fiscal year shown are from the selected line on the main screen.

Description

This non-editable field displays the description of the transaction. The descriptions that display in this field are account names for direct costs, pool names for indirect costs, and profit for profit and profit percentages.

Depending on the transaction type, you can use the Labor Detail, Transaction Detail, Pool Detail, or Profits subtask to get more detailed information on this transaction.

Subperiod

This non-editable field displays the subperiod amount for direct cost, burden, or profit.  The amount displayed in this field depends on the description in the Description field.

Subperiod Budget

This non-editable field displays the subperiod budget for direct cost, burden, or profit.  The amount displayed in this field depends on the description displayed in the Description field.

Subperiod Variance

This non-editable field displays the subperiod variance for direct cost, burden, or profit.  The amount displayed in this field depends on the description displayed in the Description field.

Period

This non-editable field displays the period amount for direct cost, burden, or profit.  The amount displayed in this field depends on the description in the Description field.

Period Budget

This non-editable field displays the period budget for direct cost, burden, or profit.  The amount displayed in this field depends on the description displayed in the Description field.

Period Variance

This non-editable field displays the period variance for direct cost, burden, or profit.  The amount displayed in this field depends on the description displayed in the Description field.

YTD

This non-editable field displays the year-to-date amount for direct cost, burden, or profit.  The amount displayed in this field depends on the description in the Description field.

YTD Budget

This non-editable field displays the year-to-date budget for direct cost, burden, or profit.  The amount displayed in this field depends on the description displayed in the Description field.

YTD Variance

This non-editable field displays the year-to-date variance for direct cost, burden, or profit.  The amount displayed in this field depends on the description displayed in the Description field.

ITD

This non-editable field displays the inception-to-date amount for direct cost, burden, or profit.  The amount displayed in this field depends on the description in the Description field.

ITD Budget

This non-editable field displays the inception-to-date budget for direct cost, burden, or profit.  The amount displayed in this field depends on the description displayed in the Description field.

ITD Variance

This non-editable field displays the inception-to-date variance for direct cost, burden, or profit.  The amount displayed in this field depends on the description displayed in the Description field.

Total Commitments

This non-editable field displays the total commitments for the project.

Labor Detail

Select this link to open the Labor Detail subtask, which contains a table window that displays the period, subperiod, GLC, PLC, Name, transaction description, hours, amount, journal, journal entry number, voucher number, posting user, entry user, reference 1, reference 2, and transaction comments for the labor transactions in the Project Status Child table window.

Transaction Detail

Select this link to open the Transaction Detail subtask, which contains a table window that displays the period, subperiod, name, transaction description, amount, journal, voucher number, purchase order number, journal entry number, check number, cash receipt number, posting user, entry user, reference 1, reference 2, and transaction comments for the rows in the Project Status Child table.

Pool Detail

Select this link to open the Pool Detail subtask, which contains a table window that displays the account, organization, subperiod burden, period burden, and year-to-date burden for the rows in the Project Status Child table window.

Profits

Select this link to open the Profits subtask, which contains a table window that displays the description, subperiod, subperiod budget, subperiod variance, period amount, period budget, period variance, year-to-date amount, year-to-date budget, year-to-date variance, inception-to-date amount, inception-to-date budget, inception-to-date variance, and total commitments for the rows in the Project Status Child table.