GLC LABOR SUMMARY

Use this subtask to view project labor grouped by the General Labor Category (GLC) charged. Employee timesheet detail is posted to the Labor History table as part of the Labor Distribution posting. The process that creates the report table for the Labor Summary report summarizes this information by project, fiscal year, period, subperiod, and GLC.

Because data displayed in the table window is from the Project Labor Summary Report table, you must create that table for the project and subperiod needed before using the inquiry.

Fiscal Year

This non-editable field displays the fiscal year that you entered when you created the project report table.

Period

This non-editable field displays the period that you entered when you created the project report table.

Subperiod

This non-editable field displays the subperiod that you entered when you created the project report table.

Rate Type

This non-editable field displays the rate type from the main screen.

Organization

This non-editable field displays the organization that was used in the transaction.

Project

This non-editable field displays a project number for the project. The project name displays in the field to the right.

Pd of Performance

This non-editable field displays the period of performance for the project.

Customer Name

This non-editable field displays the customer name for the project.

Contract Value

These non-editable fields display the contract value for the project.

Cost

This non-editable field displays the cost portion of the contract value for this project.

Fee

This non-editable field displays the fee portion of the contract value for this project.

Total

This non-editable field displays the total contract value for this project.

Table Window

The labor summary table window summarizes labor charges for the project and organization selected by GLC. The table window displays current subperiod, period-to-date, Year-to-Date (YTD), and Inception-to-Date (ITD) hours and amounts charged to each GLC. The current subperiod and period are those you selected, and are carried forward from the main screen. The YTD and ITD fields are as of the subperiod selected.

Empl Detail

Click this button to view employee detail for the selected GLC. This detail is also stored in the Project Labor Summary report table.

Hours

These fields display the total number of hours in the table.

Amount

These fields display the total amounts in the table.