Use this screen to define the options you will use when operating Costpoint Material Requirements Planning. Most of the parameters control how MRP will perform its functions, but you can use the Default Values group box to define default values for planned orders.
Set up this screen when you initialize Costpoint Material Requirements Planning and maintain it whenever changes are needed in the control parameters.
Select this checkbox to exclude customer repair Manufacturing Orders (MOs) as a source of MRP supply.
Select this checkbox to include partially released manufacturing bills of material when creating requirements.
Select this checkbox to have Costpoint Material Requirements Planning calculate the estimated cost of planned orders and exception messages.
Use the drop-down box to select how extra quantities of purchased parts will be allocated if minimum lot size conditions exist. Options are:
Ignore - Select this option to leave the extra quantities unordered.
Allocate - Select this option to allocate the extra quantities to the same inventory abbreviations requiring the material on a weighted-average basis. This is the default.
Common Stock - Select this option to allocate the extra quantities to a common stock inventory abbreviation.
Use the drop-down box to select how extra quantities of manufactured parts will be allocated if minimum lot size conditions exist. Options are:
Ignore - Select this option to leave the extra quantities unordered.
Allocate - Select this option to allocate the extra quantities to the same inventory abbreviations requiring the material on a weighted-average basis. This is the default.
Common Stock - Select this option to allocate the extra quantities to a common stock inventory abbreviation.
Select this checkbox to include pending or in-approval sales orders as a source of MRP demand.
Select this checkbox to include pending inventory requests as a source of MRP demand.
Select this checkbox to include project safety stock as a source of MRP demand.
Select this checkbox to allow maintenance of manufacturing orders in the Maintain MRP Action Messages screen.
Select this checkbox to allow maintenance of purchase orders in the Maintain MRP Action Messages screen.
Select this checkbox to allow maintenance of reservations in the Maintain MRP Action Messages screen.
Enter the days needed to pack the parts required on sales orders. This will be subtracted from the ship-by date to determine the need date.
Use this drop-down box to choose how to apply part order policy rules when executing the Update Material Requirements Plan application. Valid options are "All Parts," "Assemblies Only," and "None."
Select this checkbox to set the default to combine planned orders with each other for parts purchasing.
Select this checkbox to set the default to combine planned orders with each other for parts manufacturing.
Use the drop-down box to select the transfer type to be assigned to the transfer reservation created in Costpoint Material Requirements Planning. Options are "Standard" and "Borrow/Payback."
Enter, or use Lookup to select, the requisition approval process to be assigned to requisitions if an approval process cannot be automatically assigned.
Enter, or use Lookup to select, the planner to be assigned to requisitions and manufacturing orders if a planner cannot be automatically assigned.
Use this drop-down box to select the default MRP option code to be assigned to new inventory projects. Available options are:
Project-No CS: For common stock and non-common stock parts, supply and demand calculations are based only on the specified inventory project.
Project-CS: For common stock parts, supply and demand calculations include the specified project, along with other projects that have an MRP Planning Option Code of "Project-CS," "Top-Level Project-CS," "Netting Group-CS," or "All Projects." For non-common stock parts, supply and demand calculations are based only on the specified project.
Top-level Project-No CS: For common stock parts, supply and demand calculations are based on the specified inventory project, along with other projects that have the same top-level project as the specified project and have an MRP Planning Option Code of "Top-level Project-No CS." For non-common stock parts, supply and demand calculations are based on the specified inventory project, along with other projects that have the same top-level project as the specified project and have an MRP Planning Option Code of "Top-level Project-No CS" or "Top-level Project-CS."
Top-level Project-CS: For common stock parts, supply and demand calculations include the specified project, along with other projects that have an MRP Option Code of "Project-CS," "Top-Level Project-CS," "Netting Group-CS," or "All Projects." For non-common stock parts, supply and demand calculations are based on the specified inventory project, along with projects that have the same top-level project as the specified project and have an MRP Planning Option Code of "Top-level Project-No CS" or "Top-level Project-CS."
Netting Group-CS: For common stock parts, supply and demand calculations include the specified project, along with other projects that have an MRP Option Code of "Project-CS," "Top-Level Project-CS," "Netting Group-CS," or "All Projects." For non-common stock parts, supply and demand calculations are based on the specified inventory project, along with other projects that have the same netting group as the specified project and have an MRP Planning Option Code of "Netting Group-CS" or "Netting Group-No CS."
Netting Group-No CS: For common stock parts, supply and demand calculations are based on the specified inventory project, along with other projects that have the same netting group as the specified project and have an MRP Planning Option Code of "Netting Group-No CS." For non-common stock parts, supply and demand calculations are based on the specified inventory project, along with other projects that have the same netting group as the specified project and have an MRP Planning Option Code of "Netting Group-CS" or "Netting Group-No CS."
All Projects: For common stock parts, supply and demand calculations include the specified project, along with other projects that have an MRP Option Code of "Project-CS," "Top-Level Project-CS," "Netting Group-CS," or "All Projects." For non-common stock parts, supply and demand calculations include the specified project, along with other projects that have an MRP Option Code of "All Projects."
No MRP Planning - Use this option to select inventory rows with a part key that belongs to the selected Inventory Project. MRP will not consider inventory in projects of this type.
Select this pushbutton to access the MRP Corporate Settings subtask. You will have access to the settings in this subtask if your User ID has maintenance rights for the company ID when you first log into Costpoint.