RespreadServiceArguments Properties |
The RespreadServiceArguments type exposes the following members.
Name | Description | |
---|---|---|
AllowInProgress |
Determines whether in-progress control accounts and work packages are respread.
Optional.
| |
ClassList |
The list of cost classes that will be respread.
Required.
| |
Criteria |
The criteria to use for the respread process.
Default is 'Total Project'.
The available criteria will change based on the project and the terms and codes defined on the project.
Some typical criteria include:
* Total Project
* Control Account (the Control Account term)
* Work Package (the Work Package term)
* WBS (the name given to the CA1 key field)
* OBS (the name given to the CA2 key field)
* WP (the name given to the WP key field)
* Resource
* Resource Assignment
* CAM (the Control Account Manager term)
| |
IncludeChildren |
Determines whether the respread process will include child elements of the selected criterion.
Optional.
Default is false.
| |
Log |
Determines the comment, change number and 'significant' setting for changes that affect the log. See ProjectAuditLogDescription.
| |
PeriodFilter |
The period range to respread.
Optional.
Default is All so all periods are respread.
| |
Project |
The project that will be respread.
| |
Selection |
The the criteria filter that controls the portion of the project that is respread.
The selection must be consistent with the Criteria setting.
Ignored if Criteria is set to Total Project. Required for all other Criteria values.
Examples:
* If Criteria = "Control Account", use a Control Account key value: 1.1 / 1000
* If Criteria = "WBS", use a WBS ID: 1.2.1
* If Criteria = "Resource", use a resource ID: ASTRO
* If Criteria = "Resource Assignment", use a Resource Assignment key: 1.2 / 1200 / 01 / ASTRO
|