ReplanServiceArguments Properties |
The ReplanServiceArguments type exposes the following members.
Name | Description | |
---|---|---|
AllowCompleted |
Determines whether to replan completed work packages.
Optional.
Default is the selected value of 'Allow completed Work Package to be replanned' option in project preferences.
| |
AllowPlanned |
Determines whether to replan work packages that have not yet started.
Optional.
Default is the selected value of 'Allow planned Work Package to be replanned' option in project preferences.
| |
CreateNewWP |
This option is ignored if the ReplanMethod is SetBudgetAndProgress and the project's capture level is Control Account.
Determines whether to create a new work package for Replanned Budget/Progress/Acutal Costs during the replan.
Optional.
Default is the selected value of 'Create a new Work Package for replanned Budget/Progress/Actual costs' option in project preferences.
| |
Criteria |
The criteria to use for the replan process.
Default is 'Total Project'.
The available criteria will change based on the project and the terms and codes defined on the project.
Some typical criteria include:
* Total Project
* Control Account (the Control Account term)
* Work Package (the Work Package term)
* WBS (the name given to the CA1 key field)
* OBS (the name given to the CA2 key field)
* WP (the name given to the WP key field)
* Control Account.Location
* Work Package.Charge Number
* CAM (the Control Account Manager term)
* Work Package Manager
| |
ExtendFinishDate |
This option only applies if the UseAdjustingEntry is true and the status date is after the baseline finish date of the work package.
Determines whether the work package baseline finish date is changed to the day after the status date if the status date is after the work package baseline finish date.
Optional.
Default is the selected value of 'Extend the Work Package finish date when replanning after the baseline finish date' option in project preferences.
| |
IncludeChildren |
Determines whether the replan process will include child elements of the selected criterion.
Optional.
Default is false.
| |
Log |
Determines the comment, change number and 'significant' setting for changes that affect the log. See ProjectAuditLogDescription.
| |
NewWPDescription |
This option only applies if one of the following conditions are met:
1. CreateNewWP is true
2. ReplanMethod is SetBudgetAndProgress and the project's capture level is Control Account.
The description of the new work package.
Optional.
| |
NewWPName |
The name of the new work package that the replan process will create.
This option is required if at least one of the following conditions are met:
1. CreateNewWP is true
2. ReplanMethod is SetBudgetAndProgress and the project's capture level is Control Account.
| |
NewWPNameIsSuffix |
This option is ignored when ReplanMethod is SetBudgetAndProgress and the project's capture level is Control Account.
Determines whether the NewWPName will be applied as a suffix to the existing work package name.
Optional.
Default is false which means that the NewWPName will be applied as a prefix.
| |
ProgressAdjustmentClass |
The class where the progress of the replanned work package is stored.
Optional.
Default is the first of the following:
* the selected value of 'Alternate class for replanned Progress adjustments' option in project preferences if specified,
* Earned class if exists,
* EV class if exists,
* first Progress class defined in the project.
| |
Project |
The project that will be replaned.
| |
ReplanMethod |
Determines how the replan should be calculated.
Optional.
Default is SetBudgetAndProgress.
| |
Selection |
The the criteria filter that controls the portion of the project that is replanned.
The selection must be consistent with the Criteria setting.
Ignored if Criteria is set to Total Project. Required for all other Criteria values.
Examples:
* If Criteria = "Control Account", use a Control Account key value: 1.1 / 1000
* If Criteria = "WBS", use a WBS ID: 1.2.1
| |
UseAdjustingEntry |
Determines whether to make an adjustment in the current period when replain is performed.
Optional.
Default is the selected value of 'Replan by adjusting entry' option in project preferences.
|