AdvanceCalendarServiceArgumentsUseStatusDateAsActualStartDateForLoE Property

Determines whether to set work packages with Level of Effort (LOE) Earned Value technique and with start dates set before the new status date will be set to In-Progress. Optional. Default is false.

Namespace:  Cobra.WebService.ClientAPI.Application.Files
Assembly:  Cobra.WebService.ClientAPI (in Cobra.WebService.ClientAPI.dll) Version: 8.4.717.3176 (8.4.0717.3176)
Syntax
C#
public Nullable<bool> UseStatusDateAsActualStartDateForLoE { get; set; }