Respread

The Respread utility lets you respread budget costs for an entire project at one time or to respread the budget of an individual code of the project. This is useful when the calendar has been changed.

For example, changing the calendar from a monthly to a weekly calendar would require respreading.

When a spread curve is assigned to the resource assignment, Cobra will use it during respread. When Manual spread curve is assigned, or the spread curve is not specified, Cobra uses the existing profile of the resource assignment during respread. Use the Respread Wizard to perform the respread process.

In addition to respreading, this utility generates all calculated costs for the work.