Resource and Code Assignment Validations Page of the Validity Check Wizard

Use this page to check if resource and code assignments in the project have invalid referenced data or undefined results.

Contents

Field Description
Fix undefined results

Select this check box to validate that the resource assignment uses a result that is defined in Resource Calculation. Cobra fixes undefined results.

T-phase has invalid resource code

Select this check box to verify that each time-phase record has a valid resource code.

Resource assignments have budget, but no T-phase

Select this option to determine resource assignments that have budget at complete (BAC) data but have no time phasing data.

Resource assignments have calculation defined

Select this check box to validate the following:

  • That resources assigned in the Project view are resource values included in the resource code file attached to the project.
  • That the resource assignments used in a control account or work package have calculations in the resource file.
Key field code assignments still exist in code file

Select this check box to validate whether the values assigned from the key field codes exist in the code file. This validates CA1 (Control Account 1), CA2 (Control Account 2), CA3 (Control Account 3), and work package key fields.

Note: The validity check runs only for the Master Project selected. The validity check does not run against all the sub projects listed under the master project.