Use this page to indicate the level at which budget changes are captured.
This is also the level at which you are prompted to enter change comments or numbers for budget changes.
You cannot track budget changes at both the Control Account and Work Package levels.
Set Log Level
Field | Description |
---|---|
Control Account | Select this option to indicate that budget changes are prompted and captured at the control account level of the project. |
Work Package | Select this option to indicate that budget changes are prompted and captured at the work package level of the project. |
Resource Assignment | Select this option to indicate that budget changes are prompted and captured at the resource assignment levels of the project. |