Use the Apportionment Definition tab of the Resource view to define resource apportionment.
To define resource apportionment, complete the following steps:
-
Display the Resource view.
-
In the Resource view, select a resource or child resource from the grid. This is the resource that Cobra will apportion.
-
Select the Apportionment Definition tab.
-
On the Apportionment Definition tab pane, select the
Resource budgeted by apportionment option.
Note: If you do not select this option, the fields and options on the Apportionment Definition tab will remain unavailable.
-
Use the
Source Result drop-down list to result that you want to associate with the apportioned resource.
-
Click
Add to display the Resource Lookup dialog box, where you can select the resource that you want to use as the source for the apportioned resource. You can select multiple resources or child resources.
-
Click
Select to add the selected base resource to the
Source Resources field.
-
Click
on the Quick Access Toolbar to save the apportioned resource.
Note: The order number indicates the order by which the selected resource is calculated with respect to other resources. Each apportioned resource can be calculated from one or multiple resources within the same resource file.