Time-phase Pane of the Project View
The Time-phase pane displays the time-phased costs associated with the selected resource in the Spreadsheet pane.
Use the Time-phase pane of the Project view to:
- View resources assigned to the selected work package in the Spreadsheet pane
- Select specific resources to view by a single class, multiple classes, all classes, or reporting set
- Select specific resources to view by resource assignment code
- View the TOTAL value for each result type, for example, all HOURS in a control account for a particular resource
- Toggle the result displayed to view resource values in HOURS, FTE, DIRECT, or TOTAL DOLLARS, and the totals at the control account or work package level
- Collapse or hide resources
- Display the total time-phased spread at the control account or work package level if the Show Summary option in the Data group is selected
The data displayed in the Time-phase pane depends on the following selections:
- If the View Totals item in the EPM SA is disabled, the Total Currency is not displayed in the Result drop-down list.
- If the View Derived Results item in the EPM SA is disabled, the Result drop-down list displays only the base results of the resource assignments and the Show Summary option is also disabled. The Show Summary option becomes enabled only if you select Total Currency in the Result drop-down list. If the result selected in the Result drop-down list is the base result, the Time-phase pane does not display any roll-up data.
- If the result selected in the Result drop-down list is not the base result of the selected resource assignment, the Time-phase pane does not display any data.
- Related Topics:
- Time-phase Pane Field Descriptions
You cannot insert or remove columns in the Time-phase pane of the Project view. - Data Entry
You can manually adjust the spread of the resources within the control account or work package dates in the Time-phase pane.
Parent Topic: Project View