Reclass Preferences
Use this dialog box to select the options for running the Reclass utility, which allows you to change, copy, or replace an existing cost class.
The Reclass utility is useful when you have performed “what-if” budgeting and want to change these costs to a standard budget class such as CB. It is also possible to copy existing budget costs to either actual or forecast cost classes or to copy an actual cost class to a forecast class.
Contents
Field | Description |
---|---|
Allow reclass of completed Control Account and Work Package | Select this option to run the Reclass process against control accounts and work packages that have a status of Completed.
Cobra uses the value of this option if you run the Reclass API process and do not include the AllowComplete setting in the API script. Cobra displays an error if the Secure check box for this option is selected and the value of this setting does not match the value of the AllowComplete setting in the API script. |
Selected | Selecting this check box for any of the options makes the option selected by default in the process wizard where it is located. |
Secure | Selecting this check box for any of the options prevents users from changing the setting for that particular option in process wizards where these options are also located. Cobra uses this feature to secure certain options while users run processes against projects.
If the Secure check box is selected, this option cannot be modified on the options pages of the Cobra process wizards. Select this option to ensure that all users are using the same settings when running Cobra processes. |