Default Field Mappings

Touchstone uses a standard import template to import data from project schedules based on the schedule type (Open Plan, Microsoft Project, or Primavera P6). This topic lists the default field mappings when files are uploaded to Touchstone.

The Field Type and Baseline columns list attributes that are associated with a field extracted from the source. They are used when the project file is scored.

Touchstone Field Microsoft Project Field Open Plan Field P6 Field Loading Type Field Type Baseline
Activity Constraint PrimaryConstraint PrimaryConstraint cstr_type Normal
Activity Status Activity Status Status status_code Normal
Activity Type Activity Type Activity Type task_type Normal
Actual Cost Tsk.ActualCost ACWPcum ActualCost Actual Cost
Actual Duration Tsk.ActualDuration ActualDuration act_drtn_hr_cnt Actual Duration
Actual Finish Tsk.ActualFinish AFDATE act_end_date Normal
Actual Start Tsk.ActualStart ASDATE act_start_date Normal
Actual Work Tsk.ActualWork ACWP_QTY act_wirk_qty Actual Work
ACWPAC Tsk.ACWP ACWPcum ACWP (AC) Actual Cost
At Completion Duration At Completion Duration At Completion Duration total_drtn_hr_cnt Spread Duration
Baseline Cost Baseline Cost Baseline Cost Baseline Cost Spread Cost Yes
Baseline Duration Baseline Duration B01~ORIG_DUR Baseline Duration Spread Duration, Work Yes
Baseline Finish Baseline Finish BFDATE Baseline Finish Spread Duration Yes
Baseline Start Baseline Start BSDATE Baseline Start Spread Duration Yes
Baseline Work Baseline Work BAC_QTY Baseline Work Spread Work Yes
BCWPEV Tsk.BCWP BCWPcum BCWP (EV) Actual Cost
BCWSPV Tsk.BCWS BCWScum BCWS (PV) Actual Cost
Budget Cost Budget Cost BACcum Budget Cost Spread Cost Yes
CPI - Labor Units CPI - Labor Units CPI - Labor Units CPI - Labor Units Normal
Critical Tsk.IsCritical IsCritical IsCritical Normal
Description Tsk.Name DESCRIPTION task_Name Normal
Duration Percent Complete DurationPercentComplete DurationPercentComplete DurationPercentComplete Normal Percent
Duration Uncertainty Distribution DurationUncertaintyDistribution DSHAPE Duration Uncertainty Distribution Normal
EAC EAC EAC EAC Spread Cost
Early Finish EarlyFinish EFDATE early_end_date Normal
Early Start EarlyStart ESDATE early_start_date Normal
Earned Value Technique Earned Value Technique Earned Value Technique Earned Value Technique Normal
Earned Value Work Earned Value Work Earned Value Work Earned Value Work Actual Work
Existence% Existence% Existence % Existence% Normal Percent
ExpectedFinish ExpectedFinish XFDATE expect_end_date Normal
External Early Start ExternalEarlyStart ExternalEarlyStart external_early_start_date Normal
External Late Finish ExternalLateFinish ExternalLateFinish external_late_end_date Normal
Finish Finish Finish Finish Normal
Free Float FreeFloat FREEFLOAT free_float_hr_cnt x 60 Normal Percent
ID Tsk.Id ACT_ID task_id Normal
Is Level Of Effort IsLevelOfEffort IsLevelOfEffort IsLevelOfEffort Normal
Is Remaining Duration Elapsed IsRemainingDurationElapsed IsRemainingDurationElapsed IsRemainingDurationElapsed Remaining
LateFinish Tsk.LateFinish LFDATE late_end_date Normal
LateStart Tsk.LateStart LSDATE late_start_date Normal
Longest Path Tsk.IsCritical IsLongestPath driving_path_flag Normal
Max Duration MaxDuration DHIGH Max Duration Remaining Duration
Maximum Lag MaximumLag MaximumLag MaximumLag Normal
Mean Duration MeanDuration Mean Duration Mean Duration Remaining Duration
Min Duration MinDuration DLOW Min Duration Remaining Duration
Minimum Lag MinimumLag MinimumLag MinimumLag Normal
Most Likely Duration ModeDuration Most Likely Duration Mode Duration Remaining Duration
Number Of FF Predecessors NumberOfFFPredecessors NumberOfFFPredecessors NumberOfFFPredecessors Normal
Number Of FF Successors NumberOfFFSuccessors NumberOfFFSuccessors NumberOfFFSuccessors Normal
Number Of FS Predecessors NumberOfFSPredecessors NumberOfFSPredecessors NumberOfFSPredecessors Normal
Number Of FS Successors NumberOfFSSuccessors NumberOfFSSuccessors NumberOfFSSuccessors Normal
Number Of Lags NumberOfLags NumberOfLags NumberOfLags Normal
Number Of Leads NumberOfLeads NumberOfLeads NumberOfLeads Normal
Number Of Predecessors NumberOfPredecessors NumberOfPredecessors NumberOfPredecessors Normal
Number of Resource Assignments COUNT(ResourceAssignments) COUNT(ResourceAssignments) COUNT(ResourceAssignments) Normal
Number Of SF Predecessors NumberOfSFPredecessors NumberOfSFPredecessors NumberOfSFPredecessors Normal
Number Of SF Successors NumberOfSFSuccessors NumberOfSFSuccessors NumberOfSFSuccessors Normal
Number Of SS Predecessors NumberOfSSPredecessors NumberOfSSPredecessors NumberOfSSPredecessors Normal
Number Of SS Successors NumberOfSSSuccessors NumberOfSSSuccessors NumberOfSSSuccessors Normal
Number Of Successors NumberOfSuccessors NumberOfSuccessors NumberOfSuccessors Normal
Original Duration OriginalDuration ORIG_DUR target_drtn_hr_cnt x 60 Spread Duration
Outline Level OutlineLevel OutlineLevel OutlineLevel Normal
Percent Complete PercentComplete Progress_Percent Percent Complete Normal Percent
Percent Complete Type PercentCompleteType PercentCompleteType complete_pct_type Normal
Physical % Complete PhysicalPercentComplete PPC phys_complete_pct Normal Percent
Planned Value Work Planned Value Work Planned Value Work Planned Value Work Actual Work
Primary Constraint PrimaryConstraint PrimaryConstraint cstr_type Normal
Primary Constraint Date Tsk.ConstraintDate PrimaryConstraintDate cstr_date Normal
Project Time Now StatusDate StatusDate StatusDate Normal
Remaining Cost Tsk.RemainingCost ETC RemainingCost Remaining Cost
Remaining Duration Tsk.RemainingDuration RemainingDuration remain_drtn_hr_cnt x 60 Normal
Remaining Earned Work Remaining Earned Work Remaining Earned Work Remaining Earned Work Remaining Work
Remaining Work Remaining Work ETC_QTY remain_work_qty_ x 60 Remaining Work
ResumeDate Tsk.Resume ResumeDate resume_date Normal
Schedule % Complete Schedule % Complete Schedule % Complete sched_complete_pct Normal Percent
Secondary Constraint Secondary Constraint SecondaryConstraint cstr_type2 Normal
Secondary Constraint Date Secondary Constraint Date SecondaryConstraintDate cstr_date2 Normal
SPI - Labor Units SPI - Labor Units SPI - Labor Units SPI - Labor Units Normal
Start Start Start Start Normal
Start Percentage Start Percentage STARTPC Start Percentage Normal Percent
Sub-Project APA.SubProject Sub-Project Sub-Project Normal
SuspendDate Tsk.Stop SuspendDate suspend_date Normal
Total Cost TotalCost TotalCost TotalCost Spread Cost
Total Duration TotalDuration TotalDuration TotalDuration Normal Duration
Total Float TotalFloat TOTALFLOAT total_float_hr_cnt Normal Percent
Total Work Work Total Work total_work_qty Spread Work
Units Percent Complete UnitsPercentComplete UnitsPercentComplete UnitsPercentComplete Normal Percent
Variance - BL Finish Date Variance - BL Finish Date Variance - BL Finish Date Variance - BL Finish Date Spread Duration
Variance - BL Start Date Variance - BL Start Date Variance - BL Start Date Variance - BL Start Date Spread Duration
WBS WBS WBS WBS Normal
WBS Code WBS [BK3 file does not have a WBS Code] WBS Normal
WBS Name WBS [BK3 file does not have a WBS Name] wbs_name Normal