You must select the
Import External Activities option to import external activities.
To select the
Import External Activities option:
-
Click
.
-
Navigate to the view for the project type you want to import.
- Platforms (Deltek) for Open Plan
- Platforms (Oracle) for Primavera P6
- Platforms (Microsoft) for an MSP project
Note: Acumen does not import external activities from Microsoft Project Server.
-
Select
Import External Activities. For more information about this field, see
Importing External Activities.
-
Click
OK to close the dialog box.
-
Import your project.
Acumen imports the external activities into the project and they display in gray in the Activities view on the S1 // Projects tab. If you select one, you can see the predecessor/successor information on the Activity Relationships sub-tab. The external activities count towards the total activity count, they display in the activity grid, and they are included in metric calculations.