Compare multiple cost/schedule risk driver result sets on the same chart.
To compare risk driver results and analyze risk mitigation benefits, complete the following steps:
-
On the S3 // Risk Tab, select a project.
-
Click
.
-
In the Analysis group, click the
Run Risk Analysis down arrow and select
Uncertainty and Risk Events (No Mitigation).
-
In the Analysis group, click
Run Risk Analysis.
-
After the results display in the Risk Drivers chart, in the Risk Drivers group, click
Add to Comparison.
-
Repeat steps 1 - 5 as many times as needed, changing the mitigation option in step 3 as needed.
-
In the Views group, click
.
The Risk Driver Comparison chart displays.
-
(Optional) Click
, then select
Copy to Clipboard (just the graph) or
Copy Table to Clipboard (just the table) to copy the results, which you can then paste into another application such as MS Excel.