Deltek Acumen Options (Platforms - Microsoft)
Select the Microsoft products to which you want to link, and set related options.
Get External Data From
The products that you select here display on the S1 // Projects tab in the Get External Data From menu group.
Field | Description |
---|---|
Microsoft Project | Selecting this option allows you to link to a Microsoft Project file. With Microsoft Project, Acumen links to Microsoft Project (MSP) files using your installed copy of MS Project or by directly reading an .MPP file (without needing MS Project installed on your computer). |
Microsoft Project Server |
Selecting this option allows you to link to a Microsoft Project Server file. With Microsoft Project Server, Acumen downloads the project data from the Project Web App (PWA) site into Acumen.
If you change the server type, you need to close and re-start Acumen in order for the change to take affect. |
Microsoft Excel | Selecting this option allows you to link to a Microsoft Excel file. Acumen's interface with Microsoft Excel provides an open and flexible means of linking to external data. Any data that can be stored as an XLS or XLSX file can be imported into Acumen for analysis. |
Microsoft Project
Field | Description |
---|---|
Field to use for Activity Comparison in Forensics | Specify the field that Acumen Forensics should use to uniquely identify an activity. You can select
UniqueId,
Id,
Guid, or
WBS.
This setting only applies to MS Project. For MS Project Server, Acumen always uses Guid. |
Load Microsoft Project MPP files: |
You can load Microsoft Project MPP files in one of two ways:
|
If the "Acumen ID" Field Is Present, Map it to "Id" | Select this option to modify the default mapping when Acumen imports a project from Microsoft Project. Microsoft Project does not have an equivalent to Acumen's
ID field. Selecting this option allows Acumen's ID fields to be preserved when a project is:
When Acumen exports data for Microsoft Project, it creates a user-defined field called Acumen ID. When Acumen imports a project from Microsoft Project, it looks for the user-defined field called Acumen ID. If you select this option, values from the Acumen ID field are loaded into Acumen's ID field, thus preserving the content. This setting applies to both MS Project and MS Project Server. |
Import External Activities |
Use this field to specify whether or not Acumen imports external activities when you import a Microsoft project. When you select this option (default setting), Acumen imports the external activities into the project and they display in gray in the Activities view on the S1 // Projects tab. If you select one, you can see the predecessor/successor information on the Activity Relationships sub-tab. The external activities count towards the total activity count, they display in the activity grid, and they are included in metric calculations. When you clear this option, Acumen still imports the external activities but only uses them to resolve relationships. The external activities do not count towards the total activity count, you cannot see them in the activity grid, and they are not included in metric calculations. The only place you can see them is on the Activity Details Relationships tab. |
Load All Subprojects | Sometimes when you import a Microsoft Project master project, MSP cannot find some of the subprojects. For example, they may have been moved, or the master project may no longer have access to them. When you import a master project into Acumen and MSP cannot find one of the subprojects, as soon as one of the subprojects is missing, the import stops until you navigate to MSP and manually locate the subproject or click
Cancel
to stop looking for the subproject.
In order to prevent the import from stopping, you can clear this option and Acumen will not attempt to import the subprojects. After the import is finished, Acumen displays a log with the list of subprojects that were not imported. If you select this option, you will need to manually find each missing subproject in MSP each time there is a missing subproject. |
Field Mapping
Select one of these options to have Acumen either apply the default field mapping template or a specified template when you import data. If the field mapping template includes code fields or user defined fields, they will be applied regardless of whether or not the Automatically Map User Defined Fields to Projects and Automatically Map Code Fields to Projectsoptions on the Platforms (General) view are selected.
Field | Description |
---|---|
Use built in field mapping | Select this option if you want to use the standard field mapping template. Clear if you want to specify a template in which case you will need to specify a location and file in the field below. |
Default field mapping location | Specify the default field mapping location and file. This field is disabled if you select Use build in field mapping. |
Resource Element of Cost Field | Identify a resource field that includes EOC values for the resource.
The selected fields should only have the following values:
|