S3 // Risk Tab

Acumen Risk is an advanced risk analysis tool for managing both cost and schedule risk exposure within a project (or multiple projects). It can work either alongside, or apart from, Acumen Fuse and Acumen 360.

Acumen Risk incorporates utilities such as Monte-Carlo simulation and an integrated project risk register, together with risk approaches such as Uncertainty Factors and Risk Contribution reporting.

Acumen Risk is designed for planners, schedulers, risk analysts, and risk workshop facilitators. It is created for ease of use with meaningful reporting that doesn't rely upon complex statistical interpretation. That is, it is designed for project teams wanting to determine their cost and schedule risk exposure together with establishing a sound plan for risk exposure reduction.

As part of the Acumen platform, all common platform capabilities, such as importing from multiple scheduling tools and running forensics, are included in Acumen Risk.

You can use the S3 // Risk tab to (among other things):
  • View, assign, import, and export uncertainty values.
  • View, import, and export risk registers.
  • Perform cost and schedule risk analysis.
  • Determine the most common critical paths.
  • Report, publish, and print risk results.

Platforms Supported for Risk Analysis

The following platforms are supported for use with Acumen's Risk Analysis:

  • Microsoft Project Professional
  • Microsoft Project Server
  • Primavera P6 Web
  • Primavera P6 XER
  • Primavera P6 XML
  • Phoenix Project Manager
  • Open Plan
  • Open Plan BK3 (backup file)
  • IPMDAR
  • UN/CEFACT
  • Safran Project

If you import a project from any other platform, you will not see the project on the S3 // Risk tab.