Copy a Risk Register and Risk Mappings to a Cost Model

As a cost risk user, when you already have risks mapped to activities in a schedule and you create a cost model from your cost-loaded schedule, you can copy the risk register and risk mappings to the cost model.

To copy the risk register and risk mappings to the cost model:

  1. On the S3 // Risk tab, in the Risk Models menu group, click the Create Cost Estimate down arrow.
  2. Click Generate From Schedule > Generate With Overlay / Generate Without Overlay > With a copy of Risk Register / Without a Copy of Risk Register.
    If you Generate With Overlay, Acumen overlays every activity in the cost model to every activity in the schedule.