This tab displays information about risk events that have been mapped to the selected activity.
Field | Description |
Remove
|
Click to remove the risk event from the selected activity.
|
Mapping
Field | Description |
Activity
|
This column lists the activity ID and description.
|
Event
|
This column lists the name of the risk event.
|
Shape
|
Use these setting to specify whether you want Acumen to only calculate minimum and maximum or also calculate most likely.
- Uniform (default): Select to calculate minimum and maximum. When you select this option, the
Most likely Duration and
Most Likely Cost columns are disabled.
- Triangle: Select to calculate minimum, maximum, and most likely. When you select this option, the
Most Likely Duration and
Most Likely Cost columns and enabled and included in the calculation.
|
Current
All of the values in this section depict the current situation with no mitigation.
Field | Description |
Min Probability
|
This column lists the minimum percentage probability of the risk event occurring.
|
Max Probability
|
This column lists the maximum percentage probability of the risk event occurring.
|
Min Duration
|
This column lists the minimum duration increase that the activity will experience when the risk event occurs.
|
Most Likely Duration
|
When
Type
=
Triangle, this column is enabled and Acumen includes the most likely duration in the calculations. This column is disabled when
Type = Uniform.
|
Max Duration
|
This column lists the maximum duration increase that the activity will experience when the risk event occurs.
|
Min Cost
|
This column lists the minimum cost increase that the activity will experience when the risk event occurs.
|
Most Likely Cost
|
When
Type
=
Triangle, this column is enabled and Acumen includes the most likely cost in the calculations. This column is disabled when
Type = Uniform.
|
Max Cost
|
This column lists the maximum cost increase that the activity will experience when the risk event occurs.
|
Mitigation
Field | Description |
Duration
|
This column lists the mitigation duration.
|
Cost
|
This column lists the mitigation cost.
|
Mitigated
Field | Description |
Min Probability
|
This column lists the minimum percentage probability of the risk occurring if the risk is mitigated.
|
Max Probability
|
This column lists the maximum percentage probability of the risk occurring if the risk is mitigated.
|
Min Duration
|
This column lists the minimum duration increase that the activity will experience if the risk is mitigated.
|
Max Duration
|
This column lists the maximum duration increase that the activity will experience if the risk is mitigated.
|
Min Cost
|
This column lists the minimum cost increase that the activity will experience if the risk is mitigated.
|
Max Cost
|
This column lists the maximum cost increase that the activity will experience if the risk is mitigated.
|