Import Group on the Metrics Tab

Use the import command to merge a metric template library into an existing workbook.

When you import a metric template library, Acumen performs the following actions:
  • Metrics
    • Merges metrics based on the metric GUID (globally unique identifier). Imported metric definitions replace existing definitions if the metric already exists in Acumen.
    • Adds metrics that don't already exist in the current metric library.
    • Leaves existing metrics if they don't have an imported equivalent.
    • Adds variables and project variables that are in the file being imported that are not in the current metric library.
  • Metric Folders
    • Merges metric folders based on the metric folder GUID. Imported folder definitions replace existing definitions if the folder already exists in Acumen.

      If the folder location is in a new location in the imported library, that new location is used.

    • Adds folders that don't already exist in the current metric library.
    • Retains existing folders if they don't have an imported equivalent.
Field Description
Open

You can use this menu option to merge a metric template into an existing workbook. Click to display the File Open dialog box where you can select a metric template file that you want to merge into the current workbook.

When you import a metric template library, Acumen performs the following actions:
  • Merges metrics based on the metric GUID (globally unique identifier). Imported metric definitions replace existing definitions if the metric already exists in Acumen.
  • Adds metrics that don't already exist in the current metric library.
  • Leaves existing metrics if they don't have an imported equivalent.
  • Merges variables, project variables, and calculated fields based on the name of the item.
  • Adds variables, project variables, and calculated fields that are in the file being imported that are not in the current metric library.
  • Leaves current values for project variables unchanged after the merge. Project variable descriptions will be updated by the import.
  • Updates variables (workbook variables) based on imported values.
Note: You cannot change the data type of variables and project variables through the merge process; Acumen displays an error and stops the merge.