Range Mapping Between Acumen and PPM Risk

Use this to retrieve the probability and impact range values from PPM Risk to compare with Acumen.

When you choose Import Risks from PPM Risk, Acumen maps values between its system and that of PPM Risk. When it finds that the Acumen Risk Template and PPM Risk are not in sync, a dialog will display the differences between the two.

PPM Risk has a range limit of five for impact types and probability. Acumen has a higher range limit, allowing users a maximum of ten for both impact types and probability. If Acumen and PPM Risk have different ranges, their risk matrix score will likely differ. This can result in different risk impacts on the project

When you choose to move forward with the import process despite the differences in value ranges, you accept the potential differences in risk impacts.