Import / Publish Group on the S3 // Risk Tab
Use the commands in this group to import or publish (export) a risk register.
Print Preview
Select one of these options to preview the view. You can then save, print, export, or email the view. Some of the options are only available when that view is selected in .
- Activities
- Risk Register
- Uncertainty Inputs
- Risk Exposure
- Risk Drivers
- Risk Comparison
- Scatter Chart
- Critical Schedule Drivers
Excel
| Field | Description |
|---|---|
| Import Risk Register from Excel | Select this option to import a risk register from MS Excel. |
| Export Risk Register to Excel | Select this option to export a risk register to MS Excel. |
| Import Activity Uncertainty | Select this option to import uncertainty as absolute values (Min, Most Likely, Max, and so on) or percentage values (Min %, Most Likely %, Max %, and so on). |
| Export Activity Uncertainty | Select this option to export the Min, Most Likely, Max and so on, values for non-complete activities to an Excel file. |
Copy to Clipboard
Select an option from this drop-down list to copy visible charts to the clipboard for pasting into other applications. The available options change depending on the panel views.
- Screen Image: Use this option to copy the current image to the clipboard (WYSIWYG).
- Extended Image: Use this option to copy all of the bar rows and data to the clipboard even if some of it is not visible due to scrolling.
For the cash flow chart, an additional option is displayed under Copy to Clipboard, namely Cash Flow. Use this option to copy the cash flow chart to the clipboard.
Publish
Use this menu to generate a Risk Executive Briefing Report.
| Field | Description |
|---|---|
| Executive Briefing | Publish a Risk Executive Briefing of the current project.
|
| Selection Sets | Use this menu to set up or edit your selection sets. A selection set is a collection of activities and hierarchy nodes that you want included in the Risk Executive Briefing Report. |
PPM Risk
| Field | Description |
|---|---|
| Import Risks from PPM Risk | Select this option to link a PPM Risk project to your Acumen project.
You can choose from a pre-determined list of projects or you can create a new project. |
| Export Risks to PPM Risk | Select this option to get a list of risks that are assigned to your PPM Risk project.
You can compare and export risks using the dialog box. |
- Related Topics:
- Import Risks from PPM Risk
Import a risk register from PPM Risk to connect an Acumen project with a PPM Risk project. - Export Risks to PPM Risk
Export a risk register to PPM Risk after you have linked an Acumen project with a PPM Risk project. - PPM Risk Comparison Dialog
Use these dialog boxes to compare risks from Acumen and PPM Risk to import and/or export. - Range Mapping Between Acumen and PPM Risk
Use this to retrieve the probability and impact range values from PPM Risk to compare with Acumen. - Connect PPM Risk Project Dialog
Use this dialog box to link your Acumen project with a PPM project.