Redistribute Planned Hours
Use the Redistribute Hours feature on the Labor tab of the Plan form to replace planned hours with actual hours and spread the difference into a selected future time range, or to change the planned hours value for a selected assignment range.
You can redistribute hours for any WBS element at any level of the structure if that element has resources assigned.
- Related Topics:
- Replace Planned Hours with Actual Hours for an Assignment Range
You can replace the original planned hours with the actual hours and spread the difference into a selected time range for any level of the project structure, as long as there are resources assigned to the level.