Use this procedure to set a target cost for the project using the Cost tab of the Project Properties dialog box.
To set a target cost for the project:
-
Take one of the following actions:
- In the Projects folder of Open Plan Explorer, right-click a project and then click Properties on the shortcut menu.
- In the Project Views folder in Open Plan Explorer, display a project in any view and then click Properties in the Dialogs menu group of the Processes tab.
- In the Project Properties dialog box, click the Cost tab.
- In the Target Total Cost field, enter a target cost.
- Click OK.