Customize a Date Scale

Use this procedure to customize the date scale.

To customize the date scale:


  1. In the Project Views folder of Open Plan Explorer, display a project in barchart, multitable barchart, or histogram view.
  2. Take one of the following actions:
    • On the View tab, click Date Scale.
    • Right-click the date scale or the histogram portion of the view, and click Edit Date Scale on the context menu.
  3. On the Options tab of the Date Scale Preferences dialog box, select colors for the text and the background of the date scale.
  4. Enable a scaling tab by selecting one of the following options:
    • Manual Scaling
    • Reporting Calendar
  5. Select the tab you enabled, and make any needed modifications.
  6. When your changes are complete, click OK to return to the view.

Related Topic