Customize a Date Scale
Use this procedure to customize the date scale.
To customize the date scale:
- In the Project Views folder of Open Plan Explorer, display a project in barchart, multitable barchart, or histogram view.
-
Take one of the following actions:
- On the View tab, click Date Scale.
- Right-click the date scale or the histogram portion of the view, and click Edit Date Scale on the context menu.
- On the Options tab of the Date Scale Preferences dialog box, select colors for the text and the background of the date scale.
-
Enable a scaling tab by selecting one of the following options:
- Manual Scaling
- Reporting Calendar
- Select the tab you enabled, and make any needed modifications.
- When your changes are complete, click OK to return to the view.
Related Topic
Related Procedure
Parent Topic: Date Scale Procedures