Perform Trace Logic from Selected Activities

Use this procedure to trace logic from selected activities.

To trace logic:

  1. Open an activity spreadsheet, a resource or an activity barchart, or a network view.
  2. Select an activity to which you want to trace logic.
  3. Open the Open Plan Logic Trace Facility dialog box by taking one of the following actions:
    • From the Processes tab of the activity spreadsheet, resource or activity barchart, or network view, select Trace Logic.
    • From the context menu of an activity spreadsheet, a resource or an activity barchart, or a network view, select Trace Logic.
  4. Select or enter the necessary information.
  5. Click OK.