Time-Phased View Options Dialog Box

Open Plan includes time-phased schedule progress charts that you can use to report by activity count or values.

You can use these charts to view, for example, early/late activity completion curves with actuals as well as time-phased task completions vs baseline plan.

Use the Time-Phased View Options dialog box to set the view parameters.

Attention: For more information about the time-phased views, see Time-Phased Reporting View.

Tabs

The Time-Phased View Options dialog box contains the following tabs:

  • Options: Use this tab to specify whether to display the data by count or value and specify how the view displays.
  • Counts: Use this tab to select the attributes that you want to use when you display the activities by count.
  • Values: Use this tab to select the From and To dates and the field to spread across those dates.

Resizing

A grabber pad in the bottom right corner of a dialog box indicates that the dialog box is resizable. Click and drag the sides of the dialog box to resize.