Set Time Now Without Performing Time Analysis

Use this procedure to set Time Now and perform Time Analysis when using the Resource Scheduling Options dialog box to perform resource scheduling.

To set Time Now without performing Time Analysis:

  1. Open the project.
  2. Right-click the project folder.
  3. On the shortcut menu, click Properties.
  4. In the Project Properties dialog box, click the Status tab.
  5. In the Time Now field, enter the new status date.