Select Target Activity Dialog Box

Use the Select Target Activity dialog box to select a target activity to identify the critical path.

The list that it displays does not include completed, summary, or hammock activities. When you enter an activity ID for any of the excluded activities, Open Plan displays a warning message.

Note: Selecting an activity displays the corresponding Baseline Finish Date as well as the Constraint Date on the DCMA Constraint Metric Critical Path Analysis dialog box.