Replace a Requested Resource with a Suggested Resource

Use the Activity Resource Allocation dialog box to replace a requested resource.

To replace a requested resource with a suggested resource:

  1. In Open Plan Explorer, display a project in any view except Histogram View and Risk View.  
  2. Take one of the following actions:
    • Select the activity for which you want to replace resources, and click Allocate in the Resources menu group of the Edit tab.
    • Right-click the activity, and click Allocation on the shortcut menu.
  3. In the Activity Resource Allocation dialog box, select the assignment, and click Accept.
  4. To return to the view, click OK.

Related Topic