Project and Subproject Information
Review more details about project and subproject information.
Project Information
Each time you perform a time analysis, Open Plan calculates the following information for the project:
- The computed status of the project as follows:
- Planned
- In-progress
- Complete
- The latest early finish date in the project
- The latest late finish date in the project
- The percentage of the total project duration that is complete
- The minimum value for total float for any activity (or activities) in the project
- The number of in-progress activities
- The number of completed activities
Subproject Information
Open Plan calculates the following information for each subproject (both internal and external) during time analysis:
- The duration of the subproject
- Early and late dates
- The remaining duration for the subproject if its activities are in progress
Parent Topic: Time Analysis