Multiple Calendars
Open Plan contains a powerful calendar function that allows you to use any number of calendars to control when work can be performed.
In addition to the default project calendar, you can also have specific calendars for activities, relationships, and resources that require exceptions to the default calendar.
For example, while the default calendar for a project may specify a 5-day work week, a part-time resource on the project may work only 3 days a week. This resource would need a specific calendar to reflect that schedule.
Parent Topic: Working with Calendars