Lock a Requested Resource
Use the Activity Resource Allocation dialog box to lock a requested source.
To lock a requested resource:
- In Open Plan Explorer, display a project in any view except Histogram View and Risk View.
-
Take one of the following actions:
- Select the activity for which you want to lock resources, and click Allocate in the Resources menu group of the Edit tab.
- Right-click the activity, and click Allocation on the shortcut menu.
- In the Activity Resource Allocation dialog box, select the assignment, and click Lock.
- To return to the view, click OK.
Related Topics
Parent Topic: Related Procedures